My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

Can employees with caring responsibilities be placed on Flexible Furlough?

Employees who are unable to work because they have caring responsibilities resulting from the coronavirus can continue to be furloughed. For example, employees that need to look after children can be furloughed, as you have previously submitted a claim for them in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June.

As more people return to work, there is an increased chance of more parents having childcare issues until Schools are fully open. However, they can’t be placed on furlough unless they had been on it before. So it would likely be unpaid leave, unless the government amends the scheme to grant an exemption.

How is the Court of Protection dealing with matters during the Coronavirus pandemic?

The current situation with the coronavirus pandemic has presented obvious challenges to the effective and fair operation of the Court of Protection (COP). Remote access to the COP has therefore become a necessity to ensure that hearings continue to provide proper access to justice. All parties involved in such cases have a responsibility in achieving this primary aim.

What are the existing legal obligations to conduct a suitable and sufficient assessment of risk for a workforce, and where particular characteristics require it, for individuals?

It is the individual assessment by an organisation of its Covid-19 risk in its workplace that will be central. There may be common features across sites or areas of a site but every workplace will have a different risk profile depending on the service it offers and the workers who deliver those services.  No one size fits all.

The context of managing Covid-19 risk is the need to tie in with UK government guidance and HSE advice – which despite being a lot more comprehensive than it was, is not a panacea and will continue to evolve.  The difficulty we have with this in the context of the known increased risk to BAME employees from Covid-19 is that our understanding of the risk is, we would suggest, at a pretty early stage which makes it more difficult to address. However we know the increased risk exists and we owe our BAME workers a duty to manage that risk and keep them safe.

We also have a duty to consult employees.  This is critical in managing this risk – ensuring BAME workers have a loud voice in the assessment process will be very important.

Where an individual has a particular characteristic, for instance they’re pregnant, they have physical or mental disabilities etc, the law requires us to look at that individual or, where it is a group, that group of individuals and assess the risk to them and take any reasonably practicable steps to control the risk to them.

Risk control hierarchy is key. In “normal” businesses we reduce our Covid-19 risk by keeping people away from the workplace – “avoid, eliminate and substitute” then changing work practices (e.g. social distancing measures) before we arrive at PPE. In a healthcare context, we arrive at PPE a lot more quickly.

We need to ensure our people are given sufficient information, instruction and training so they can do their jobs safely and we must consult workers and involve them in workplace safety – this is going to be critical in the context of Covid-19.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Which agreements will qualify for exemption?

There are four criteria which must be satisfied if an agreement is to be considered exempt:

  • It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
  • It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
  • It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
  • It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).