My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
The guidance is non-statutory and is not binding on business. However, businesses should be aware that there might be reputational consequences if they do not follow the guidance; we have already seen in the context of taking advantage of furlough funding that not being in breach of the law is no protection against negative publicity. Further to the extent a contract expressly requires parties to act reasonably, it could be expected that this guidance is one of the factors a court would consider in determining what is reasonable.
In our latest “in conversation” webinar we discussed the outlook for the corporate transaction market. Whilst it would be a brave person to predict the future of anything at the moment given current circumstances, we were joined by two organisations who are very well placed to provide their views.
John Laud, Head of Corporate Banking for North and West Yorkshire for Barclays, his colleague Stephen Loureda from their Credit Analysis Team, and Jill Williams, Investment Director of Mercia Asset Management’s Growth Fund, were in conversation with Ward Hadaway corporate partners Adrian Ballam and Jonathan Pollard to share their thoughts about how the ‘new normal’ for the transactions market may look:
- With supply chain and forecast prediction challenges, how will banks and investors determine what represents a sound opportunity?
- How will distressed and opportunistic acquisition opportunities be funded, and what is investor appetite for such opportunities?
- How have seller and buyer pricing expectations been impacted as a result of the pandemic?
- How are funders reacting, and how should ambitious businesses respond to the very low, or even negative, interest rates?
We expect this video to be of real value to those businesses whose plans of buying, selling or investment may have been impacted by the current economic crisis, but who are looking at opportunities to determine how they may shape their futures – #gettingbacktobusiness.
Employers and employees can decide the split of the hours of work and the hours of furlough. There is no maximum or minimum requirements. You can change the arrangement, by agreement, from time to time.
When claiming for employees who are flexibly furloughed, you should not claim until you are sure of the exact hours they will work during the claim period.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland. In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:
- £30 million for the Scottish Government
- £20 million for Welsh Government
- £10 million for the Northern Ireland Executive
There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.