My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
Hosted by NewcastleGateshead Initiative, Partners Damien Charlton and Jane Garvin discussed in this webinar contracts, managing supply chains and the role of directors, with a particular focus on cancellation of events and businesses in the tourism and hospitality sector.
You can find a recording of the webinar from NGI here.
Employees who are unable to work because they have caring responsibilities resulting from the coronavirus can continue to be furloughed. For example, employees that need to look after children can be furloughed, as you have previously submitted a claim for them in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June.
As more people return to work, there is an increased chance of more parents having childcare issues until Schools are fully open. However, they can’t be placed on furlough unless they had been on it before. So it would likely be unpaid leave, unless the government amends the scheme to grant an exemption.
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
The FCA’s test case in the Supreme Court ruled overwhelmingly in favour of policyholders. However, business interruption cover generally has the prerequisite of physical damage or loss to the property (or in some circumstances, the presence of a notifiable disease at the property or within a certain radius of it), to recover losses caused by the interruption to your business. The onus is on insurers to re-assess those claims which are impacted by the Supreme Court’s judgment and to make contact with the policyholders regarding next steps. If you have not already made a claim, in the first instance the terms of any policy should be checked carefully to see whether business interruption cover is provided.