Skip to content

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

What other factors may be considered?
  • Integration:
    • Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
  • Exclusivity:
    • Is the contractor restricted from working for other organisations without the consent of the end user client?
  • Length of engagement:
    • Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
  • Pay:
    • Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
  • Facilities:
    • Does the contractor provide their own equipment and materials to provide the services?
  • Financial risk:
    • Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.

Are there any differences in employment status for employment law or for tax purposes?

The key factors for determining status for employment and tax purposes are generally the same. However there are some cases that highlight the different approaches taken by employment tribunals and HMRC when determining status. The important thing to consider for IR35 purposes is that being deemed employed for tax purposes does not mean a contractor is ’employed’. PSC’s can still be used in moving forward but there are likely to be discussions on the commercial aspects of the contractor arrangement. Employment status for tax purposes is likely to come at a cost for both parties.

ONLINE EVENT: Contracts, managing supply chain issues and the role of directors

Hosted by NewcastleGateshead Initiative, Partners Damien Charlton and Jane Garvin discussed in this webinar contracts, managing supply chains and the role of directors, with  a particular focus on cancellation of events and businesses in the tourism and hospitality sector.

You can find a recording of the webinar from NGI here.