Skip to content

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

Can I offer credits or re-booking as an alternative to a refund?

The financial implications of having to repay all deposits and advance payments could be very serious for some businesses. As an alternative to a refund, many are offering customers the opportunity to re-book at a later date, or a voucher that can be redeemed against a subsequent booking.

The CMA’s view on this practice is that consumers can in many situations be offered alternatives of this type, but they should not be “misled or pressured” into accepting this. Their view is that a refund should be an option that is just as clearly and easily available. The CMA also points out that any restrictions that apply to credits, vouchers, re-booking or re-scheduling, such as the period in which credits must be used or services re-booked, must also be fair and made clear to consumers.

The full CMA guidance re “The Coronavirus (Covid-19) pandemic, consumer contracts, cancellation and refunds” can be found here.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Have you had any safeguarding issues in relation to staff they see and do you follow your normal safeguarding pathway?

Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.

Who decides on carrying-over holiday entitlement?

The Regulations do not require any prior agreement between an employer and employee that it was not reasonably practicable for holiday to be taken for it to be carried over.

However, if an employee requests holiday then an employer must have ‘good reason’ for refusing it due to coronavirus. The term ‘good reason’ is not defined so the Government will expect employers, employees and (if necessary on any dispute) the Courts to apply common sense.

The Regulations are not confined to key workers so could, in principle, be used by employers for a wider range of employees.

The Government guidance suggests that the following factors should be taken into account when considering whether it was reasonably practicable to take the leave in the relevant year:

  • Whether the business has faced a significant increase in demand due to COVID-19 that would reasonably require the worker to continue to be at work and cannot be met through alternative practical measures.
  • The extent to which the business’ workforce is disrupted by COVID-19 and the practical options available to the business to provide temporary cover of essential activities.
  • The health of the worker and how soon they need to take a period of rest and relaxation.
  • The length of time remaining in the worker’s leave year.
  • The extent to which the worker taking leave would impact on wider society’s response to, and recovery from, the effects of COVID-19.
  • The ability of the remainder of the available workforce to provide cover for the worker going on leave.
What if I have missed the January deadline for submitting my 2018/2019 tax return?

You had until 23 April 2020 to submit your return in order to be considered for eligibility.