Skip to content

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Related FAQs

What processes can I adapt regarding Housing Disrepair?

As we all adjust and adapt in line with the Government’s guidance throughout this uncertain time, we must consider how we can revise current processes and implement new ones to maintain effective and compliant ways of working. We have identified several key issues that all housing providers should consider.

Protocol Compliance

Housing providers will continue to receive new disrepair claims. Throughout the disruption caused by coronavirus, landlords will still be expected to respond to these claims and comply with the Pre-Action Protocol for Housing Conditions Claims whilst doing so. We address the issue of disclosure in particular below.

Letters of claim will continue to be sent by post to your Registered Office, and the deadlines will run from the date of deemed service. Ensure you have systems to enable you to scan correspondence and forward it to the responsible officer who will handle the claim so deadlines are met.

Under the Protocol, the deadline for disclosure is 20 working days from deemed service of a letter of claim (2 working days after it is sent). So, for example, a letter dated 2 March 2020 would be deemed served on 4 March 2020 and disclosure would therefore be due by 1 April 2020. All housing providers must continue to comply with the Protocol and so landlords should begin preparing now.

Failure to meet deadlines often result in the issuing of further applications to court by tenant’s solicitors which in turn will lead to unnecessary costs orders against landlords.

Therefore, all records, particularly relating to customer contact and repair logs, should be held electronically. If required, this will allow for such documentation to be redacted for GDPR purposes remotely and disclosed to the tenant’s solicitor simply and efficiently.

Remember it is possible to request an extension to all Protocol deadlines and it is inevitable in these unusual times, this will need to be utilised, and should not be refused. Request extensions to deadlines at the earliest opportunity to enable an achievable timescale. It would be a difficult lawyer that would not agree to such a request.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

How do I set the hours that my employees will work under the Flexible Furlough Scheme?

Employers and employees can decide the split of the hours of work and the hours of furlough. There is no maximum or minimum requirements. You can change the arrangement, by agreement, from time to time.

When claiming for employees who are flexibly furloughed, you should not claim until you are sure of the exact hours they will work during the claim period.

Reductions in salary

An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.

Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.

Can I use my Public and Employer's Liability insurance to protect my business from a claim?

Business operators such as travel operators, hotels and restaurants remain vulnerable to claims of failure to protect against contracting the virus. There is a high chance of claims from employees, clients and members of the public. These are likely to be covered under public liability and employer’s liability insurance.