My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Related FAQs

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
Can you ask employees for evidence of the requirement to self-isolate under the Test and Trace scheme?

Yes, you can ask to see any information/documentation sent to an employee informing them that they should self-isolate.

I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?

No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.

Where can I find more Companies House guidance?

Companies House guidance on the impact of coronavirus on their services can be found at: https://www.gov.uk/guidance/coronavirus-guidance-for-companies-house-customers-employees-and-suppliers

This flexibility offered by Companies House could be a useful short-term help to businesses that are struggling to deal with the impact of the Covid-19 outbreak, but be sure to take action in advance of your filing deadline.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.