My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Related FAQs

Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

How much notice do I need to give people to return to work?

There is no minimum period of notice you are required to give employees of their return, but from a good HR practice point of view you should be speaking to your staff and letting them know what the plan is; giving people a reasonable amount of notice of return will allow them to prepare both practically and psychologically.

Are there any differences in employment status for employment law or for tax purposes?

The key factors for determining status for employment and tax purposes are generally the same. However there are some cases that highlight the different approaches taken by employment tribunals and HMRC when determining status. The important thing to consider for IR35 purposes is that being deemed employed for tax purposes does not mean a contractor is ’employed’. PSC’s can still be used in moving forward but there are likely to be discussions on the commercial aspects of the contractor arrangement. Employment status for tax purposes is likely to come at a cost for both parties.

How is the Court of Protection dealing with matters during the Coronavirus pandemic?

The current situation with the coronavirus pandemic has presented obvious challenges to the effective and fair operation of the Court of Protection (COP). Remote access to the COP has therefore become a necessity to ensure that hearings continue to provide proper access to justice. All parties involved in such cases have a responsibility in achieving this primary aim.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.