My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Related FAQs

My business has a contract with a public sector body – what guidance has the Government issued about payment under contracts between public and private sector bodies?

The Cabinet Office has published a helpful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). This can include making advance payments to suppliers, if necessary. The PPN sets out actions that public sector bodies should take (until at least 30 June 2020) to ensure continuity of service and to ensure that its suppliers can resume normal contract activity once able to.

The actions public sector bodies should be taking include:

  • Informing its suppliers (that they believe are at risk) that they will continue to be paid as normal until the end of June 2020 (even if service delivery is currently interrupted). Risk might include supply chains collapsing and/or significant financial implications for a supplier
  • If a contract involves a payment by results mechanism, basing payments on previous months (e.g. the average monthly payment over the previous 3 months), and
  • Ensuring that invoices submitted by suppliers are paid immediately to maintain cash flow in the supply chain and help to protect jobs.

If you are a supplier to a public sector body, you must act transparently and on an open-book basis, making cost data available to your public sector clients. You must also continue to pay your employees and subcontractors / suppliers. Suppliers to the public sector must not expect to make profits on any undelivered elements of a contract. The PPN makes clear that, should suppliers be found to be taking undue advantage, or failing to act transparently, a public sector body can take action to recover payments made to that supplier.

The PPN requires public sector bodies to urgently review their contract portfolios and take steps to support suppliers who they believe are “at risk”. However, no definition of “at risk” is given in the document.  We would suggest that if you are a supplier and you have yet to hear from a public sector client, you should seek to get in touch with them as soon as possible, particularly if you have concerns about your supply chain, staff retention and/or are experiencing financial difficulties currently. Given the requirement for transparency, you may be required to provide evidence, so it may be helpful to have any relevant documentation ready to send, if necessary, as this may help ensure a decision is made by the public sector client more promptly, particularly as the public sector body may have a number of contracts to consider.

 

What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

What is the guidance in relation to the Mental Capacity Act 2005 and Deprivation of Liberty Safeguards during the Covid-19 pandemic?

The Department of Health & Social Care has published guidance for hospitals, care homes and supervisory bodies on the Mental Capacity Act 2005 (MCA) and Deprivation of Liberty Safeguards (DoLS) during the coronavirus pandemic.

In many scenarios created or affected by the pandemic, decision makers in hospitals and care homes will need to decide:

  • if new arrangements constitute a ‘deprivation of liberty’ (most will not), and
  • if the new measures do amount to a deprivation of liberty, whether a new DoLS authorisation will be required (in most cases it will not be).

If a new authorisation is required, decision makers should follow their usual DoLS processes, including those for urgent authorisations.

A summary of the key points to be taken from the guidance is outlined below:

Use of the MCA and DoLS due to Covid-19

  • During the pandemic, the principles of the MCA and the safeguards provided by DoLS still apply.
  • It may be necessary to change the usual care and treatment arrangements, for example to provide treatment for people with Covid-19, to move them to a new hospital or care home to better utilise resources or to protect them from becoming infected.
  • All decision makers are responsible for implementing the emergency Government health advice  and any decision made under the MCA must be made in relation to a particular individual, it cannot be made in relation to groups of people.

Best interest decisions

  • In many cases, a best interests decision will be sufficient to provide the necessary care and treatment for a person who lacks the capacity to consent to the care and/or treatment arrangements during this emergency period.
  • If an individual has made a valid and applicable advance decision to refuse the treatment in question, then the relevant treatment, even for Covid-19, cannot be provided.

Delivering life-saving treatment

  • Where life-saving treatment is being provided in care homes or hospitals, including for the treatment of Covid-19, then the person will not be deprived of liberty as long as the treatment is the same as would normally be given to any person without a mental disorder.
  • The DoLS will therefore not apply to the vast majority of patients who need life-saving treatment who lack the mental capacity to consent to that treatment, including treatment to prevent the deterioration of a person with Covid-19.

The full guidance can be found here.

What is in the WH Toolkit?

We have developed a toolkit to assist with compliance. The Toolkit contains a specimen contract; detailed guidance; step by step guides and flowcharts; details of the factors to take into account for the status determination test; procedures for challenging the determination; and standard letters for the process.  Click here to fill in a form and register your interest in the Toolkit, which contains:

  1. Detailed guidance in the form of Key Facts
  2. Employment status checklist
  3. Employment status assessment flowchart
  4. Status questionnaire and guidance
  5. Letter confirming self-employed status (agency)
  6. Letter confirming employed status (agency)
  7. Letter confirming self-employed status (direct with PSC)
  8. Letter confirming employed status (direct with PSC)
  9. Status disagreement process guidance
  10. Status disagreement process flowchart
  11. Letter confirming outcome of status disagreement process
  12. Consultancy agreement