My planning permission is due to expire, can I extend the period for implementation?
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
With the exception of the Covid-19 Corporate Financing Facility (see below), there was initially little dedicated financial assistance for medium-sized and larger businesses affected by the coronavirus outbreak (the so-called “stranded middle”); however, from 20 April 2020 such businesses (with a turnover above £45 million) have been able to access finance via the Coronavirus Large Business Interruption Loan Scheme (“CLBILS“).
CLBILS operates in a similar manner to CBILS except that a lender can provide:
- up to £25 million to businesses with turnover from £45 million up to £250 million; and
- up to £50 million to businesses for those with a turnover of over £250 million.
Finance is available in the form of:
- term loans
- revolving credit facilities (including overdrafts)
- invoice finance and
- asset finance,
in each case available on repayment terms of up to three years.
Several changes to CLBILS took effect from 26 May 2020. The maximum amount available through CLBILS to a borrower and its group increased from £50m to £200m. Term loans and revolving credit facilities over £50m will be offered by CLBILS lenders which have secured additional accreditation. The maximum size for invoice finance and asset finance facilities remains at £50m. Companies borrowing more than £50m through CLBILS will be subject to further restrictions on dividend payments, senior pay and share buy-backs during the period of the loan. Further information on the most recent changes, including new provisions on seniority of CLBILS facilities, can be found on the CLBILS page on the British Business Bank website. There is also an in-depth FAQs section for businesses, which has the full details of the changes to the scheme.
Unlike CBILS, the UK government will not make payments to cover the interest and any lender-levied fees in the first 12 months of any facility so these larger businesses will not benefit from the no upfront costs and lower initial repayments that smaller businesses eligible for CBILS benefit from. The other key provisions of CLBILS, such as the eligibility criteria, the 80% government-backed guarantee and security, are similar to those of CBILS.
Eligibility is similar to CBILS and businesses must:
- Be UK-based in its business activity
- Have an annual turnover of more than £45 million
- Have a borrowing proposal which the lender would consider viable, were it not for the current pandemic, and for which the lender believes the provision of finance will enable the business to trade out of any short-term to medium-term difficulty
- Self-certify that it has been adversely impacted by the coronavirus (COVID-19)
- Not have received a facility under the Bank of England’s Covid Corporate Financing Facility.
Businesses from any sector can apply, except the following:
- Credit institutions (falling within the remit of the Bank Recovery and Resolution Directive), insurers and reinsurers (but not insurance brokers)
- Building Societies
- Public-sector bodies
- Further-education establishments, if they are grant-funded
- State-funded primary and secondary schools
All lending decisions remain fully delegated to the accredited lenders.
It has also been proposed in the Corporate Insolvency and Governance Bill that public companies who were due to file their accounts in the period from 26 March 2020 to 30 September 2020 will have until the earlier of the 30 September 2020 and the date which is 12 months after the end of their relevant accounting period to do this.
This is separate from the pre-existing scheme, announced on 25 March 2020, whereby companies can apply to Companies House for a 3 month extension for filing their accounts.
The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.