My mum remarried. She has now passed away and has left everything to my step-dad. I am worried that he will not leave me anything when he dies. Can my step-dad write me out of the Will?
This will depend on the arrangements your mum (or dad, as the case may be) and her spouse have made. They may have made ‘mirror Wills’ or ‘mutual Wills’. Alternatively, they may have simply made their own Wills which have totally different provisions.
If your mum and your step-dad made ‘mirror Wills’, then the surviving spouse can revoke that Will and make a new one. They may not leave you anything under their new Will, and a dispute may rise.
If your mum and your step-dad made ‘mutual Wills’, they make a legal promise not to change their Will unless they both agree to this.
Complex family structures can lead to issues and fallouts when someone dies. These circumstances are very fact-specific. You can contact us for advice and we can advise you whether we think you have a claim.
Related FAQs
Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Many charities have money that are considered restricted funds which are given to the charity or raised for a specific purpose. The Charity Commission gives guidance on this, please see the link below. Depending on the circumstances in which these monies have been given to a charity or raised you may or may not be able to use them.
Monies raised in an appeal or specific fund raising campaign are unlikely to be available as it is likely to be impossible to get the permission of the donor to change the use. If however you have had monies donated for a specific purpose and you can identify the donor you can use these funds for general overheads and to pay wages etc. if you receive the donor’s specific permission to do so.
Government guidance is that public transport should be avoided wherever possible. Transport providers will be expected to follow government guidance to make their services more COVID-19 secure.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs