My ex-husband has died and I was receiving maintenance payments from him. He hasn’t left me anything in their Will. What can I do?
You may be able to make a claim against your ex-spouse’s estate on the basis that their Will does not make ‘reasonable financial provision’ for you. You will not be able to bring a claim if you have remarried, or if a condition of your divorce explicitly states that you will not make a claim against their estate.
These types of claims are very fact-specific so it is not possible to give a straightforward yes or no answer as to whether any such claim is available to you. The court will consider all factors which we can explore with you in more detail.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.
For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Be careful, there is now a cap on the number of employees you can have on furlough at one time.
The number of employees you can claim for in any claim period starting from 1 July cannot exceed the maximum number of employees you claimed for under any claim ending by 30 June 2020. So this cap is going to be specific to each employer.
It may catch out, in particular, employers who had been rotating employees on furlough.