Is there a matched funding scheme for the National Emergencies Trust?
The government has also confirmed it will match donations to the National Emergencies Trust as part of the BBC’s Big Night In fundraiser on 23 April – pledging a minimum of £20 million.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.
Sections of the video and their timings are as follows:
(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)
(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II
(05.36) – bounce back loans have been a distraction
(06.27) – muted impact of fintech CBILS lenders
(07.52) – discussion about invoice discounting
(11.59) – looming insolvency environment
(12:52) – emerging themes
The reaction from NCVO is that this is an important first step. However, it will not stop well run charities from closing and others will look very different in a few months’ time.
The Home Office has not stated when it will end these temporary measures, albeit it has stated that it will provide a warning. Where employers have carried out checks using the temporary measures, the Home Office has confirmed that it will require employers to carry out retrospective checks on any of the following:
- Employees who started working for you when the temporary measures were in place
- Employees who required a follow up check during the temporary measures (for example because their previous leave was coming to an end).
It is not explicit from the guidance but these retrospective checks must require you to have in your possession the physical ID in its original form. When carrying out the retrospective check, employers must record this using the following wording “the individual’s contract commenced on [insert date]. The prescribed right to work check was undertaken on [insert date] due to Covid-19.”
These further checks must be made within eight weeks of the temporary measures ending, and employers must keep records of both checks undertaken. Where the employer discovers that the employee does not have the right to work during the retrospective check they should stop employing them.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here