Is my business covered by insurance for notifiable diseases?
Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.
Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.
The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.
Related FAQs
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.
- From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
- From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
- 30 September 2021: scheme closes.
Employees will continue to receive 80% of their current wages, up to £2,500 a month.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The fundamentals of risk assessment remain the same as for any other foreseeable risk.
Focus on risk controls which reflect Government guidance; social distancing (2 metres) and avoiding contact with occupiers if possible, high-quality PPE – disposable overalls, gloves and fluid repellent surgical face masks, ready access to antibacterial wipes for surfaces, tools and equipment and plentiful hand sanitizer.
A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.
The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development. The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.
The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects. A link to the Regulations is here.
The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period. They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.