Skip to content

In a situation where a building has a B1 EWS1 rating but the insurance companies are either refusing to quote or saying the cladding is a fire risk (due to the result of the intrusive survey for the EWS1 rating) and quadrupling insurance premium, is there anything that will help with this situation in the Building Safety Act or the secondary regulations when they come in or do you think it is something case law will have to address?

The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.

Related FAQs

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What if you want to terminate the contract completely?

If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:

  • Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
  • A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all

If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.

Even if the right to terminate the contract does exist, there might be particular rules about the following:

  • How much notice has to be given
  • How such notice has to be served (for example, it might have to be in writing to a particular address)
  • When the notice can be served (perhaps on an anniversary of the start of the contract)
  • How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)

All of these factors must be taken into account, and any contractual processes for termination are followed.

I’m a social housing provider. What do I do if I know my tenants are flouting the social distancing guidelines?

If a tenant continues to refuse to take heed of the government’s social-distancing guidelines, for example by inviting large groups of people who do not reside there to their property, it can constitute a nuisance. One housing association successfully applied for an injunction. The injunction ordered by the Court stipulated that no persons, other than the children of the tenant, are to attend the property until the current social-distancing restrictions are lifted by the government.

A representative of the housing association highlighted the need for the current guidelines to be followed and the need for housing providers to ensure that all residents living in their communities are kept safe during this time of ‘unprecedented risk’.

This case demonstrates that flouting of the current restrictions is likely to be considered anti-social in the eyes of the courts – a point which all housing providers should bear in mind during this period. Further, it highlights the availability of an alternative remedy to the issuing of possession proceedings (in light of the government’s moratorium on evictions) to deal with anti-social behaviour during the next three months, Covid-19 related or not.

What will be the added cost to business of furloughing staff from 1 July 2021?

Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.

  • From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
  • From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
  • 30 September 2021: scheme closes.

Employees will continue to receive 80% of their current wages, up to £2,500 a month.

 

How does this protect businesses entering into an insolvency process?

The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.

Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance,  in the event that the customer enters an insolvency procedure.

This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.

Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.

Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.