I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
Related FAQs
The Government has announced a £750 million funding package for charities to ensure they can continue their vital work during the coronavirus outbreak. This is for a 3 month period and further specific funding may be made available.
Charities which are businesses can also access the Government’s Coronavirus Business Interruption Loan Scheme (CBILS) – Please see our Funding and Finance FAQ’s.
The reporting requirements relating to cases of, or deaths from, COVID-19 under RIDDOR apply only to occupational exposure, that is, as a result of a person’s work.
You should only make a report under RIDDOR when one of the following circumstances applies:
- an accident or incident at work has, or could have, led to the release or escape of coronavirus (SARS-CoV-2). This must be reported as a dangerous occurrence
- a person at work (a worker) has been diagnosed as having COVID-19 attributed to an occupational exposure to coronavirus. This must be reported as a case of disease
- a worker dies as a result of occupational exposure to coronavirus. This must be reported as a work-related death due to exposure to a biological agent
The guidance is helpful and is likely to be useful to businesses as they seek to respond to the crisis and to restart their business activities as lockdown is eased. However, there remain outstanding questions. For example, can collaboration to prevent widespread insolvencies be viewed as in the interest of consumers? Businesses need to remain aware of the extremely high stakes involved in relation to competition law. Businesses contemplating collaboration with competitors should take legal advice before doing so.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.