I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
Related FAQs
Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.
The government introduced The Working Time (Coronavirus) (Amendment) Regulations 2020 to amend the Working Time Regulations 1998 to allow for the change.
Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.
Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.
The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here