I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
Related FAQs
Yes probably in our opinion, even if you are not considering taking any formal action against them. Ultimately if a doctor is suspended this could be considered as causing them reputational damage and it therefore is correct that they are afforded the protections (in particular in relation to keeping exclusion/suspension under review) of MHPS. Under Part V of MHPS there is provision for excluding practitioners if they are a danger to patients and they refuse to recognise it or if they refuse to co-operate. It doesn’t refer to a particular risk for the practitioner themselves, but it would appear logical that it would apply.
Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.
Potentially, yes. If someone refuses to follow the health and safety measures that have been put in place to protect them, colleagues and possibly their customers, including (where appropriate) the use of PPE then this is a disciplinary issue and should be dealt with as such. Repeated failure to comply with the requirement to follow these measures, or a one off significant failure, may be sufficient to justify dismissal, depending on the circumstances.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.