If an employer identifies that higher PPE spec is required for BAME employees undertaking a particular task, is it necessary to increase the spec for all employees working in that area?
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.
Related FAQs
The Bill allows the Secretary of State to make regulations to temporarily extend various filing date deadlines for companies. These include deadlines for filings accounts, confirmation statements, charges register, director and secretary appointments and resignations. The extended period must not exceed 42 days where the existing period is up to 21 days, or 12 months where the existing period is 3, 6 or 9 months.
The coronavirus outbreak has seen State support being given to businesses on an unprecedented scale.
This issue is likely to be increasingly relevant as Governments seek to protect and stimulate their economies as they emerge from lockdown.
How have the rules been relaxed in the context of the crisis and what facets of the existing law can be used for the State to provide support to undertakings?
The guidance has confirmed that all remaining employment rights and terms continue while an employee is furloughed. Holiday will continue to accrue during furlough however you may reach agreement with employees on reducing entitlement provided that it does not fall below the statutory minimum of 5.6 weeks per year.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.