If an employee works with vulnerable people who are at high risk of catching coronavirus, can the employer require them to limit their activities outside of work?
It is unlikely that an employer can place such a requirement on staff without infringing the employee’s privacy. If the employee is acting in accordance with the rules, limiting their activity would likely be considered unreasonable.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.
This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.
The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
It is a theoretical possibility that “anti-vax” beliefs could be a philosophical belief under the Equality Act 2010 and therefore anti-vaxers have the right not to be discriminated against for their beliefs. Much will depend on why the individual is against the vaccine. Conspiracy theorists (the vaccine is being used as an opportunity to monitor you or it’s all because of 5G) are highly unlikely to be treated as having a philosophical belief!
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.