Skip to content

If an employee works with vulnerable people who are at high risk of catching coronavirus, can the employer require them to limit their activities outside of work?

It is unlikely that an employer can place such a requirement on staff without infringing the employee’s privacy. If the employee is acting in accordance with the rules, limiting their activity would likely be considered unreasonable.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Is there anything I can do to try and settle my claim?

There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.

Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.

A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.

ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

What are some other factors?

No one factor will determine status and the outcomes will differ depending on the nature of the work being carried out and the business of the end user client.

When you have carried out an assessment based on the relevant factors you can either get in touch with us to discuss further, check your answers against HMRC’s CEST tool or do both before making a final determination.

What other financial resources are available for charities?

Charities can also take advantage of the existing measures the Government has already put in place including deferring their VAT bills, paying no business rates for their shops next year and furloughing staff where possible with the Government paying 80% of their wages under the Coronavirus Job Retention Scheme – see our People and Employment FAQ’s and our Premise and Property FAQ’s.