If a member of staff does not inform me that they ought to be self-isolating will I still be liable for a fine?
Potentially no.
If an employer is not put on notice that the circumstances of a worker or agency worker are such that they ought to be self-isolating, by either the worker or agency worker themselves or another member of staff, then there ought to be a reasonable excuse, and potentially, no fixed penalty notice will be issued.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
- Be alert to the fact that guidance on treating Covid-19 may change with emerging knowledge/scientific data and this may require subsequent modifications to treatment.
- Critical care staff should support healthcare professionals who do not routinely work in critical care but need to do so.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Government guidance is that public transport should be avoided wherever possible. Transport providers will be expected to follow government guidance to make their services more COVID-19 secure.
The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.