Skip to content

I have to pay my ex-spouse monthly spousal maintenance pursuant to a Court Order and I can no longer afford to pay. Can I stop paying?

Maintenance Orders embodied in a Court Order are variable. If you have lost a very large part of your income, then the Courts ought to take that into consideration when looking at a Court Application to reduce or end spousal maintenance payments. The outcome of any Court Application will, however, depend on a number of factors.

Technically, you should not just stop paying or reduce the maintenance payments, as your ex-spouse could then make an Application to Court for enforcement and payment of the arrears. You could ask the Court to forego you having to pay those arrears if you had evidence to prove that you could not make the payments, however, the Court will need to take a fair approach and you should not assume this request will be agreed.

You should first try to negotiate a reduction or termination of the maintenance with your ex-spouse, either directly or through a Solicitor. If this is possible, you should obtain a Court Order reflecting that agreement. Where a sensible compromise cannot be reached, a Court Application may be necessary.

Related FAQs

What payments can be included in the claim for a grant?

You can claim for regular payments you are obliged to pay staff such as non-discretionary overtime, non-discretionary fees, non-discretionary commission and piece-time payments. Overtime in this context is referred to as ‘past overtime’ in the updated guidance which would suggest that you should use the variable pay calculation (see FAQ above) for those who regularly carry out overtime.

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

Reductions in salary

An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.

Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.

What was the purpose of the Chancellor's economic update?

On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs