Skip to content

How should contracting authorities work with PFI providers?

  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.

Related FAQs

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

Who is responsible for planning in the event of an excess of deaths?

In the unfortunate event that there will be a significant number of deaths, planning will fall to the local resilience forum; which includes all relevant local organisations and statutory bodies, who will have prior experience in working in excessive death scenarios.

It is for the coroners to ensure that they are familiar with the local resilience forum plans and discussions required. This will include issues regarding storage capacity and post-mortem examination capacity.

VIDEO: Force majeure during the coronavirus pandemic

Commercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.

What agreements will the CMA choose not to take enforcement action in respect of?

CMA guidance suggests that it will not take enforcement action in respect of agreements which:

  • Are appropriate and necessary to avoid a shortage, or ensure security, of supply
  • Are clearly in the public interest
  • Contribute to the benefit or wellbeing of consumers
  • Deal with critical issues that arise as a result of the Covid-19 pandemic
  • Last no longer than is necessary to deal with these critical issues
Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.