Skip to content

How long do I have to bring a claim?

Anybody who wishes to make a claim for provision under the 1975 Act must be issue their claim at court within 6 months of the Grant of Probate being issued in the deceased’s estate.

This does mean that it is quite important to act quickly if you believe that you may wish to bring a claim under the 1975 Act against an estate.  Whilst it is possible to make an application for financial provision more than 6 months after the issue of the Grant of Probate, the court would need to be satisfied with the reasons which are provided for the delay.

Related FAQs

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

I have recently bought or sold a business. How will earn outs and deferred consideration be affected by coronavirus?

A common feature of corporate acquisitions is that part of the consideration is paid on deferred terms or by way of earn out over a period of years following completion. Where deferred consideration is payable, this is either on the basis that outstanding payments will be made on scheduled dates or, less usually, subject to certain agreed (typically financial) objectives being met. These objectives almost always relate to a period before completion of the deal and are dealt with as part of a completion accounts mechanism.

How do I determine contractor status?

You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.

Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.

The key factors used to determine status  are:

  • Control:
    • How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
  • Personal service:
    • Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
  • Mutuality of obligation:
    • Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?
My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

I’m in the process of litigation. What happens during the coronavirus outbreak?

The best advice is that parties should proceed as they would have done before the crisis began.