Skip to content

How is the Pensions Regulator reacting to the crisis?

  • The Pensions Regulator has published regularly-updated guidance for employers.
  • It will take “a proportionate and risk-based approach towards enforcement decisions … with the aim of supporting both employers and savers”. In other words, the law remains the same, but the Regulator will show restraint in enforcement against breaches.

Related FAQs

What if the contractor is supplied by an agency?

As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.

If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.

If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.

How can workers get to work safely?

The Government’s guidance says walk, cycle or drive to work and avoid public transport if you can. Businesses will need to support workers in adopting alternative travel methods to reduce exposure to the virus. You could consider staggering start and finish times for shifts to reduce commuting during peak hours, or support cycling with secure storage facilities and a drying room.

Would you suggest using a different name for a MHFA, maybe a MH champion, to encompass the wider pro-active role?

This may be a good idea – whatever name they are given, it is essential that MHFAs are empowered to take a proactive approach to organisational mental health and that they have the bandwidth to be able to discharge their responsibilities.  The name should reflect the culture of the organisation, the key aspect is awareness and accessibility – identifying a name for your company that supports this is key.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times