How important is social distancing when planning your workplace?
It is absolutely critical to creating a safe workplace and to making workers feel secure.
This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.
The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?