How have competition law rules been relaxed in the light of the coronavirus outbreak?
The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.
Related FAQs
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.
As part of the Coronavirus Bill there is some good news for tenants in so far as it included the following:
- All commercial tenants in England, Wales and Northern Ireland missing rent payments are to benefit from a government ban on forfeiture of their lease.
- Landlords then will be prevented from terminating leases and “evicting” commercial tenants.
- The above provisions rules will apply not only to principal rent, but to “any sum a tenant is required to pay”, leaving the burden of supplying services and insuring the premises on landlords. The bill will last until 30 June 2020, with an option for the government to extend this deadline.
Whist this is helpful to any Tenant planning not to pay rent or other payments due under their lease insofar as they will not suffer forfeiture and be evicted, it should be noted that the contractual obligation to continue paying rent and all other costs due under the lease remains and Landlords will still be able to take action to recover any payments due under the lease that are in arrears.
All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.
Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.
Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.
Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.
As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.