How have competition law rules been relaxed in the light of the coronavirus outbreak?
The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.
Related FAQs
The Office of the Public Guardian is continuing to accept applications to register Lasting Powers of Attorney but their usual estimated timescale of eight to ten weeks is likely to be affected by the current situation.
Consequently, an alternative or interim measure if you need something quickly is to execute a General Power of Attorney to authorise someone to act as your Attorney to undertake day to day financial transactions for you. The General Power of Appointment only needs to be executed by you in the presence of a witness (not the Attorney) to be valid and does not need to be registered with the Court of Protection. However, the Power of Attorney would cease to have effect if you become incapable of managing your affairs. It should be seen as a stop-gap only.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The current guidance issued by Mr Justice Hayden confirms that remote hearings may be conducted using the following facilities and that this will be the default position until further direction:
- By way of an email exchange between the court and the parties;
- By way of telephone using conference calling facilities;
- By way of the court’s video-link system, if available;
- The use of the Skype for Business App installed on judicial laptops;
- Any other appropriate means of remote communication, for example BT MeetMe, Zoom or FaceTime.
The key factors for determining status for employment and tax purposes are generally the same. However there are some cases that highlight the different approaches taken by employment tribunals and HMRC when determining status. The important thing to consider for IR35 purposes is that being deemed employed for tax purposes does not mean a contractor is ’employed’. PSC’s can still be used in moving forward but there are likely to be discussions on the commercial aspects of the contractor arrangement. Employment status for tax purposes is likely to come at a cost for both parties.
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved