Skip to content

How does COVID-19 affect Right to Work checks?

All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

What are the special considerations for DB schemes?
  • Before any agreed reduction in wages, actual changes to earning patterns (loss of overtime, for example) may impact the pensionable salary as defined under the scheme rules, with knock-on effects to a number of benefit calculations, such as death in service benefits.
  • Contractual changes to member salaries may adversely impact accrued benefits as the final salary figure may be reduced to a greater or lesser extent depending on the duration of furlough and the severity of any reductions in wage, and hence reductions may be difficult to agree with staff.
  • Reducing employer contributions will be subject to a number of the same considerations applicable to a DC scheme listed above. There will also be a need to change the rules and interact with the trustees, although it may be possible to override the rules with a direct contractual agreement with members.
  • Reducing employee contributions will also depend on the scheme rules, particularly as to whether there are any discretionary powers to suspend contributions, or pensionable service.
  • The rules will need to be considered for any unexpected consequences of furlough: depending on the wording of the rules, furlough may or may not be considered a leave of absence and may or may not have the effect of terminating pensionable service. This could have far-reaching consequences.
  • In particular, if the workforce’s pensionable service is inadvertently terminated as opposed to suspended in accordance with any relevant rule, this could trigger a statutory employer debt on an employer participating in a multi-employer scheme, if pensionable service continues for employees of other employers. This sort of issue is unlikely to be spotted until after the event, and therefore difficult to untangle. However, an employer should be able to take advantage of the “period of grace” provisions by notifying the trustees of its intention to re-admit employees to pensionable service within the next 12 months.
  • Clearly the impact of the Coronavirus Job Retention Scheme on DB schemes is complex and legal advice should be sought before any changes are considered.
What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What was the purpose of the Chancellor's economic update?

On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.