How does a Public Body amend its contracts to enable continued payment to contractors?
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
Related FAQs
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
Every company has to file accounts at Companies House every year. If they are filed late, a fine is automatically levied. If there is a long delay in filing them, the directors are at risk of prosecution and the Registrar of Companies might start a process which could ultimately lead to the company being struck from the register.
However, Companies House has recognised that businesses might currently face exceptional problems in preparing and filing their accounts on time and so have posted a notice on their website which says that if immediately before the filing deadline, it becomes apparent that accounts will not be filed on time due to coronavirus, you can make an application to extend the period allowed for filing.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Ultimately closing a service will be a decision that is taken at the highest level and that decision will depend on risk appetite. Often these types of higher risk are mitigated by way of insurance but that still depends on an insurer being willing to accept that risk. This decision will depend on accepting a known risk and its consequences.
The Coronavirus pandemic will have impacted businesses in many different ways, but some of the most likely impacts that could have a legal implication are as follows:
- Services were not performed in accordance with contract during the period of disruption. This could be a reduction in volume of services performed, a suspension of services, or performance in a way that does not comply with contractual KPIs
- Late delivery or non-delivery of goods because of factory closures, or disruption in the supply chain
- Changes being agreed between parties to contracts to deal with the consequences of the Covid-19 outbreak