How does a Public Body amend its contracts to enable continued payment to contractors?
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
Related FAQs
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision
In the unfortunate event that there will be a significant number of deaths, planning will fall to the local resilience forum; which includes all relevant local organisations and statutory bodies, who will have prior experience in working in excessive death scenarios.
It is for the coroners to ensure that they are familiar with the local resilience forum plans and discussions required. This will include issues regarding storage capacity and post-mortem examination capacity.
- Yes, if contributions to a defined contribution (“DC”) scheme exceed statutory minimum for auto-enrolment purposes, it may be possible to reduce employer contributions to the statutory minimum, but not further.
- However, the processes required for reduction of DC employer contributions will necessitate obtaining legal advice:
- Reducing employer contributions may require changes to the employment contracts of affected staff (as does the furlough process).
- Reducing employer contributions may also require negotiation with trade unions or other staff representative forums.
- Where group personal pensions are used, the contractual format may not permit changes of employer contributions, and hence it may also be necessary to enter into a new contractual arrangement. Choosing a new group personal pension plan is a not insignificant task in itself.
- Employers with at least 50 employees are required to conduct a 60-day consultation process with affected employees if they propose to reduce employer contributions (but please see below).
- Finally, it may require a change to the scheme rules and engagement with the scheme trustees if the scheme is operated under trust.
- For DB schemes, specific considerations apply (see the last section, below).