Skip to content

How does a Public Body amend its contracts to enable continued payment to contractors?

The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.

For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf

Related FAQs

Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What guidance has the CMA issued about how it expects businesses to behave in response to the global pandemic?

On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.

Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.

This includes the following situations:

  • Where a business has cancelled a contract without providing any of the promised goods or services
  • Where no service is provided by a business, for example because this is prevented by Government public health measures
  • A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.

In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.

This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.

The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.

What happens if someone is asked to restrict their duties but, despite acknowledging the risks to their health involved, they say that they want to continue to work on the front line?

As their employer, you have an overriding duty to provide a safe system of work. The Trust would not be able to run a defence to say that an employee “waived their rights” and chose to continue to work. Provided the decision around restricting duties has been carefully thought out, a full risk assessment undertaken and the employee has been truly consulted about the impact on them, then the decision taken will be a reasonable management instruction. Failing to follow that reasonable management instruction could amount to a disciplinary offence.

What do I do if I can't travel to the UK to activate my visa?

If your 30-day visa to travel to the UK (vignette) has expired or is about to, you can request a replacement free of charge until the end of 2020 by contacting the Coronavirus Immigration Help Centre. This can be granted with new and extended validity dates to allow travel once you are able to.