How does a Public Body amend its contracts to enable continued payment to contractors?
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
Related FAQs
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.
Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.
Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19
In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.
- On admission to hospital, all adults should be assessed for frailty, irrespective of their age and Covid-19 status. Regard should be had to any comorbidities and underlying health conditions.
- If a patient is identified as potentially having Covid-19, the UK Government guidance on infection prevention and control measures should be followed.
- If Covid-19 is then diagnosed in someone who is not isolated from admission or presentation, the UK Government guidance on actions required when a case was not diagnosed on admission should be followed.