Skip to content

How do I remain compliant and cover any risk?

Data on properties, and people, has never been more important.

Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.

It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.

Operatives need to be provided with the tools to operate in as safe a way as possible:

  • Checklist of questions to ascertain occupant’s current health
  • Protective equipment (masks, gloves, over clothing)

The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/

Related FAQs

What about office holders?

Office holders who provide services under an intermediary (such as a service company consultancy agreement) and whose services relate to the office held, would fall under the IR35 regime and must be assessed accordingly.

Is there a cap on the number of employees on Flexible Furlough?

Be careful, there is now a cap on the number of employees you can have on furlough at one time.

The number of employees you can claim for in any claim period starting from 1 July cannot exceed the maximum number of employees you claimed for under any claim ending by 30 June 2020. So this cap is going to be specific to each employer.

It may catch out, in particular, employers who had been rotating employees on furlough.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Should volunteers be DBS checked?

There is not currently a requirement for MHFAs to be DBS checked.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here