How do I go about registering a death at this time?
The Government has introduced legislation to expand the list of those who can register deaths to include Funeral Directors who are dealing with the funeral arrangements and who has been authorised by a relative of the deceased to register the death. Also, the medical cause of death certificate can be emailed to the Registrar’s office and arrangements made to have a telephone appointment to provide the Registrar with information to register the death. The requirement to attend the Registrar in person to sign the Register has been relaxed so that this is not necessary. It will however still be necessary to register the death within 5 days.
Related FAQs
The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.
It does not appear that the process applies to Confirmation Statements or other returns.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
Initially, the relaxation applied to supermarkets and food suppliers. This was subsequently widened to apply to other businesses, permitting them to collaborate where necessary to respond to the crisis in the interests of consumers.
The guidance asks parties to act responsibly and fairly in performing and enforcing contracts. They are encouraged to act in a spirit of cooperation to achieve practical, just and equitable outcomes. In essence, rather than sticking strictly to the contract as agreed, they are encouraged to give each other leeway to deliver performance differently than they are required to do under the contract.