How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
If you do not have a justifiable reason for insisting that your employees have the vaccine (see FAQ above) your employee could resign and bring a claim of constructive unfair dismissal if they have more than 2 years’ continuous employment. This would be on the basis that you have breached trust and confidence.
If the vaccine includes pig gelatine (as many do), and the employee refuses on religious or because they are vegan, you may face a claim for discrimination under the Equality Act 2010.
There is no minimum period of notice you are required to give employees of their return, but from a good HR practice point of view you should be speaking to your staff and letting them know what the plan is; giving people a reasonable amount of notice of return will allow them to prepare both practically and psychologically.
The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.
If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.
Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf