Skip to content

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

What are the contractual issues that businesses need to think about as they get back to business following lockdown?

It is clear that we are emerging from a completely unprecedented period of disruption for many businesses, and this may have had a huge impact on their contractual arrangements both with suppliers and customers.

As the lockdown eases, and we get back to business, it’s important that businesses take stock of what has happened, and ensure they review and address the legal and contractual consequences of what has been happening since the start of the global pandemic.

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Will there be further measures for self-employed announced?

The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.

The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.

 

What is the guidance in relation to the Mental Capacity Act 2005 and Deprivation of Liberty Safeguards during the Covid-19 pandemic?

The Department of Health & Social Care has published guidance for hospitals, care homes and supervisory bodies on the Mental Capacity Act 2005 (MCA) and Deprivation of Liberty Safeguards (DoLS) during the coronavirus pandemic.

In many scenarios created or affected by the pandemic, decision makers in hospitals and care homes will need to decide:

  • if new arrangements constitute a ‘deprivation of liberty’ (most will not), and
  • if the new measures do amount to a deprivation of liberty, whether a new DoLS authorisation will be required (in most cases it will not be).

If a new authorisation is required, decision makers should follow their usual DoLS processes, including those for urgent authorisations.

A summary of the key points to be taken from the guidance is outlined below:

Use of the MCA and DoLS due to Covid-19

  • During the pandemic, the principles of the MCA and the safeguards provided by DoLS still apply.
  • It may be necessary to change the usual care and treatment arrangements, for example to provide treatment for people with Covid-19, to move them to a new hospital or care home to better utilise resources or to protect them from becoming infected.
  • All decision makers are responsible for implementing the emergency Government health advice  and any decision made under the MCA must be made in relation to a particular individual, it cannot be made in relation to groups of people.

Best interest decisions

  • In many cases, a best interests decision will be sufficient to provide the necessary care and treatment for a person who lacks the capacity to consent to the care and/or treatment arrangements during this emergency period.
  • If an individual has made a valid and applicable advance decision to refuse the treatment in question, then the relevant treatment, even for Covid-19, cannot be provided.

Delivering life-saving treatment

  • Where life-saving treatment is being provided in care homes or hospitals, including for the treatment of Covid-19, then the person will not be deprived of liberty as long as the treatment is the same as would normally be given to any person without a mental disorder.
  • The DoLS will therefore not apply to the vast majority of patients who need life-saving treatment who lack the mental capacity to consent to that treatment, including treatment to prevent the deterioration of a person with Covid-19.

The full guidance can be found here.

I pay child maintenance and half of my children's private school fees to my ex-partner but I have been placed on Furlough, with no top-up from my employer, so my income has dropped significantly. Is there anything I can do?

a. You should first try and discuss this with your ex-partner, either directly or through a Solicitor, to see whether an amicable agreement can be reached.

If you contribute to private school fees voluntarily, it is a matter for you and your ex-partner to resolve the issue with the school, depending whose name is on the bills. You may need to speak to the children’s school to see whether they can offer any reductions or remedies in relation to those payments. If you contribute to the school fees as part of a Court Order, you will need to ensure you do not breach the Order and you may need to consider applying for a variation of the Order if you can no longer afford the payments or reach a compromise agreement with your ex-partner.

You can use the Child Maintenance Service (CMS) calculator (https://www.gov.uk/calculate-child-maintenance) to recalculate your child maintenance obligations using your amended income. This recalculation can then be used in your discussions and you can formally instruct the CMS to verify that calculation if you and your ex-partner cannot reach an agreement about it. If you have already formally involved the CMS, they do carry out an annual review of child maintenance payments, however, they will also recalculate payments outside of the review period where there has been a change in income of 25% or more. We expect the CMS will be experiencing a high volume of enquiries at the present time so anticipate there may be delays in them assisting.

The position on child maintenance payments included in a Court Order are slightly more complicated and how you approach this will depend on how much time has passed since the date of the Order.