How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
- Certain workers will become “furloughed workers”.
- Furloughed workers cannot carry out any work for their employer while designated as furloughed, or a linked or associated organisation but they can do voluntary work as long as they are not providing services for or generating revenue for the employer or a linked or associated organisation.
- A furloughed worker can be furloughed part time and work the rest of the time.
- The furlough period begins when the employee stops work, not when agreement is reached.
- If furloughed employees are expected to do online training while furloughed they must receive the National Living Wage/National Minimum Wage for the time spent training.
- Workers must be told of and agree to this change in writing. This written agreement must be kept for five years as part of the scheme. The guidance has confirmed that collective agreement reached between an employer and a trade union on furloughing staff is acceptable for the purposes of making a claim under the scheme.
- However it should also be noted that this is a change in status and pay (if pay is not being topped up) and therefore subject to the usual employment law rules on changing terms and conditions.
- Changes to the contract must be made by agreement with the worker and the government guidance is clear that to be eligible for the subsidy employers must document their communication with the employee on being furloughed.
- You must confirm in writing that an employee has been furloughed, but that the employee does not need to provide a written response. Please note that this is for the purposes of making a claim under the scheme. Any reduction in pay must be agreed in writing under normal employment law principles and failure to do so may result in Employment Tribunal claims. You should not rely on a term in the employment contract to effect this change. We can advise you on how to document this properly.
- Employers must also keep a record of the agreement for at least 5 years.
- If employers have collective bargaining arrangements in place, they must agree this change with the union in the usual way.
- Collective consultation obligations may be triggered if there are 20 or more employees that are proposed to be dismissed and re-engaged in order to effect the change to terms to be furloughed. You should take advice if you think this may apply.
Initially, the relaxation applied to supermarkets and food suppliers. This was subsequently widened to apply to other businesses, permitting them to collaborate where necessary to respond to the crisis in the interests of consumers.
If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.
If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract. This will involve time and legal expense.
You will claim a pro rata’d amount of 80% of salary, based on the proportion of hours not worked out of the employee’s normal working hours (their “usual” hours).
There are 2 ways to calculate an employee’s usual hours, depending on whether they have fixed or variable hours/pay:
- For those with fixed hours/pay, you take the number of hours worked in the pay period before 19 March 2020.
- For those with variable hours/pay, you take the higher of:
- the average number of hours worked in the tax year 2019 to 2020 or
- the corresponding calendar period in the tax year 2019 to 2020.
If employees are paid per task or piece of work done, you should work out the usual hours for these employees in the same way as for other employees who work variable hours, if possible.
When you calculate the usual hours, you should include any hours of leave for which they were paid their full contracted rate (such as annual leave) and any hours worked as overtime (but only if the pay for those hours was not discretionary).
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs