How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Employers should ensure that apprentices are paid at least the Apprenticeship Minimum Wage, National Living Wage or National Minimum Wage (AMW/NLW//NMW) as appropriate (and taking into account the new rates which will take effect from 1 April 2021) for training carried out where their wage received through the Coronavirus Job Retention Scheme does not cover this.
The Government introduced shielding in the peak of the pandemic. Current advice is that shielding is not required. However, those who have been shielding are likely to be the most vulnerable and will likely be nervous about a return to work. They may also be disabled under the Equality Act 2010. You should therefore consider any concerns that are expressed and take action to mitigate any risks. For example, it may be possible to keep these employees on furlough until the scheme runs out or they may be able to work from home. If you would like to discuss any specific scenarios then please contact one of the team.
Every company has to file accounts at Companies House every year. If they are filed late, a fine is automatically levied. If there is a long delay in filing them, the directors are at risk of prosecution and the Registrar of Companies might start a process which could ultimately lead to the company being struck from the register.
However, Companies House has recognised that businesses might currently face exceptional problems in preparing and filing their accounts on time and so have posted a notice on their website which says that if immediately before the filing deadline, it becomes apparent that accounts will not be filed on time due to coronavirus, you can make an application to extend the period allowed for filing.
The CMA is the government body that is responsible for protecting consumers from unfair trading practices. It has announced programme of work to investigate reports of businesses failing to respect cancellation rights during the Coronavirus pandemic.
Based on the complaints received by them from consumers, the CMA has identified three sectors of particular concern:
- Weddings and private events
- Holiday accommodation
- Nurseries and childcare providers
The CMA has expressed concern about the number of complaints that it has received about businesses seeking to retain deposits for cancelled events, undue restrictions being placed on use of vouchers provided for cancelled bookings, and payments being demanded to hold open nursery places.
The CMA has said it will prioritise investigation of these sectors, and then move on to other sectors.
- Working with PFI providers to get contingency plans up to date
- If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
- maintain unitary charge payments
- revise contract requirements/standards
moderating payment and performance regimes where appropriate.
- In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
- When putting local bespoke arrangements into place it is vital that:
- Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
- It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.