How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
The Coronavirus pandemic will have impacted businesses in many different ways, but some of the most likely impacts that could have a legal implication are as follows:
- Services were not performed in accordance with contract during the period of disruption. This could be a reduction in volume of services performed, a suspension of services, or performance in a way that does not comply with contractual KPIs
- Late delivery or non-delivery of goods because of factory closures, or disruption in the supply chain
- Changes being agreed between parties to contracts to deal with the consequences of the Covid-19 outbreak
Statutory leave includes family related leave, sick leave or parental bereavement leave. Claims for furloughed individuals returning from statutory leave should be based on their salary, before tax, and not the pay they received while on statutory leave.
Similarly, claims for furloughed employees returning from a period of unpaid leave on sabbatical should be based on their pay they would have had on paid leave.
Yes, but as a last resort. In summary, the law requires employers:
- to assess the workplace risks posed to new or expectant mothers or their babies;
- to alter the employee’s working conditions or hours of work to avoid any significant risk to them;
- where it is not reasonable to alter working conditions or hours, or would not avoid the risk, to offer suitable alternative work on terms that are not “substantially less favourable”;
- where suitable alternative work is not available, or the employee reasonably refuses it, the employer should consider whether it is appropriate to suspend the employee on full pay.
Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.