How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
You should already have a written furlough agreement with your furloughed employees, but if you move them to flexible furlough then you need a new agreement that confirms the new furlough arrangement.
So, you’ll need to speak to your employees and confirm the hours of work with them in writing (or reach a collective agreement with a recognised Trade Union.
As before, an employee does not need to provide a written response. But the agreement needs to be documented in writing.
Employees who are unable to work because they are shielding in line with public health guidance (or need to stay home with someone who is shielding) can be furloughed after 1 July 2020, as long as you have previously submitted a claim for them in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June.
The practicalities and processes regarding disrepair claims will undoubtedly be affected. Housing providers will have to adopt a risk-based approach and consider government guidance to handle claims going forward. Key points to consider are:
- Compliance with the Pre-Action Protocol for Housing Conditions Claims (particularly disclosure)
- The practicalities of inspection
- Non-urgent repairs
As long as you can demonstrate that you have exercised reasonable care in determining status you have discharged your obligations in that respect. However, if you are unable to demonstrate this, you may as the end user client be responsible for the contractor’s tax and NIC’s.
State aid rules are contained in the Treaty on the Functioning of the European Union (previously referred to as the Treaty of Rome). The State aid rules prohibit the use of state resources, or any public support with an economic value, which given selectively has the capacity to distort trade by favouring certain undertakings, or the production of certain goods, and which has the potential to affect trade between Member States. Where aid is present it must not be granted unless it has been specifically approved in advance by the European Commission or benefits from a general exemption to the rules.
In general, the rules apply to all State actions which might assist businesses including:
- Grants
- “Soft” loans
- Selling to business at an undervalue
- Buying from business at an overvalue