Skip to content

How do I access the scheme?

Those who are eligible will be contacted directly by HMRC based on tax returns they have received. If you are eligible you will be asked to fill out an online application. HMRC will pay applicants directly.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Changing to shift working

Changing to shift working may give employers the opportunity to change hours / pay whilst also focusing work when it is needed. Like the other provisions, this should be done fairly, either across the board or by selecting teams/individuals based on objective business reasons. Imposing without agreement would create significant risk, therefore would require fair selection and consultation.

What about employees who say they cannot return to work due to childcare issues?

Employers will need to be flexible with employees who are unable to return to work at present due to childcare difficulties. While schools have reopened, a period of isolation may result in employees having to keep children off school/nursery and therefore have childcare issues. Some employees will be able to manage this with their partner and extended family, whereas others will not. Where an employee simply cannot make any other arrangements to care for their children in the short term then they will be unable to return to work until that situation changes. Any dismissals on the basis that someone is unable to return to work as a result of lack of childcare are likely to be unfair, at least in the short term where such employees may well be able to demonstrate that they had no options available to them.

In a situation where a building has a B1 EWS1 rating but the insurance companies are either refusing to quote or saying the cladding is a fire risk (due to the result of the intrusive survey for the EWS1 rating) and quadrupling insurance premium, is there anything that will help with this situation in the Building Safety Act or the secondary regulations when they come in or do you think it is something case law will have to address?

The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.

What are the current planning restrictions on supermarkets, food retailers and distribution centres concerning deliveries?

On 13 March 2020 the Secretary of State for Housing, Communities and Local Government issued a Written Statement in respect of delivery restrictions.

In this respect, many supermarkets, food retailers and distribution centres in England operate under planning restrictions (conditions and/or obligations) which limit the time and number of deliveries from lorries and other delivery vehicles which can take place particularly at night primarily to protect the residential amenity of nearby residential property.

Key points in the Statement include;

  • Given the exceptional challenges facing the UK from the coronavirus, it is vital that deliveries of food, sanitary and other essential products over the coming weeks can be made as quickly and safely as possible, minimising disruption to the supply chains. The likely pressures on driver capacity mean additional flexibility is needed so that retailers can accept deliveries throughout the day and night where necessary.
  • That planning enforcement is discretionary and that local planning authorities should act proportionately in responding to suspected breaches of planning control.
  • That local planning authorities should not seek to undertake planning enforcement action which would result in unnecessarily restricting deliveries of food and other essential deliveries during this period having regard to their legal obligations.

The Statement acknowledges that the increased frequency of deliveries particularly at night could have a temporary impact on residents. It therefore concludes that the Government will review the need for the flexibility outlined in the Statement after the pressure from the coronavirus has reduced and that it is the intention to withdraw it once the immediate urgency has subsided.

A link to the Written Statement is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/