How can I tell if the correct procedure was followed when the Will was executed?
There are a number of technical formalities which any testator must follow in order to execute a valid Will. These include:
- The Will must be signed by the testator, in the presence of two other witnesses and then be signed by those witnesses, in the presence of the person making the Will after the testator themselves has signed the document.
- The person making the Will must be over 18 years of age and have mental capacity.
- The person must make the Will voluntarily without undue influence and must know and understand what the Will says; and
- The Will must be in writing
Related FAQs
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.
Borrowers will not have to pay a guarantee fee. Lenders will pay a fee to access the scheme. The Government will make a Business Interruption Payment to cover the first 12 months of interest payments and any lender-levied fees, allowing smaller businesses to benefit from no upfront cost.
British Business Bank has indicated that following earlier discussions with the banking industry, some lenders indicated that they would not charge arrangement fees or early repayment charges to SMEs borrowing under the scheme. Each business should check the terms of the loans being made to ensure this is the case and what the interest rate and prepayment fees will be following the period in which the Government makes payment of these amounts.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
No, there is no obligation on employers to offer a flexible furlough arrangement to staff. Operationally, flexible furlough may not be appropriate for your business and equally, returning on a part-time basis may not be suitable for individuals already furloughed for various reasons. Concerns about returning to work part-time or at all should be considered on a case-by-case basis.