How can I tell if the correct procedure was followed when the Will was executed?
There are a number of technical formalities which any testator must follow in order to execute a valid Will. These include:
- The Will must be signed by the testator, in the presence of two other witnesses and then be signed by those witnesses, in the presence of the person making the Will after the testator themselves has signed the document.
- The person making the Will must be over 18 years of age and have mental capacity.
- The person must make the Will voluntarily without undue influence and must know and understand what the Will says; and
- The Will must be in writing
Related FAQs
The basics of health and safety law requires that employers take “all reasonably practicable steps” to ensure workers’ safety and that a suitable and sufficient assessment of risk is undertaken. It is the individual assessment of Covid-19 risk in each workplace that will be central. Employers will be required to conduct a robust risk assessment and then, following the hierarchy of controls, put robust processes and safeguards in place to address those risks.
UK government guidance and HSE advice is continually evolving, which in practice means that any risk assessment will need to be reviewed very regularly as that guidance develops. There is flexibility for individual businesses within the overall government framework and there will need to be a process of evaluation to ensure that the measures in place continue to meet the requirements.
The starting point of avoid, eliminate and control means looking at individuals continuing to work from home where possible (the fewer the number of people back in the workplace the lower the risk), and if not look at risk management, which leads to administrative controls – i.e. changing work practices before ending up at PPE. PPE is generally seen as control of last resort but in practice – facemasks, disposable gloves and constant prompts to wash hands for example.
In terms of changing working practices, employers should be thinking about:
- the workspace and how this is laid layout
- how do we make sure it is kept clean and hygienic
- how do we keep people apart
- how can we use toilets, canteens or other shared spaces/facilities safely
- how do we promote and enable higher levels of workplace hygiene
- if we are going to rely on PPE – can we get it, and is it suitable
- what about limiting customer interactions
- will there be enough first aiders on site
- can we manage fire safety, deliveries etc
- what about higher risk workers
- should work tools and equipment be allocated on an individual basis to employees.
These decisions need to be recorded and clearly communicated to staff members.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The only potential negatives are the potential for MHFAs to become overloaded, or for MHFAs to overstep the boundaries of their role. Both would be avoided if a suitable framework is in place around them, and if adequate ongoing support and training is provided.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.
Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.