Flexible working
Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.
A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.
Related FAQs
Yes, this is very likely to amount to a reasonable management instruction which is put in place for public health reasons. Employers should make it clear to their employees that this is something they are required to do and that if they fail to do so this may lead to disciplinary action.
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
As we all adjust and adapt in line with the Government’s guidance throughout this uncertain time, we must consider how we can revise current processes and implement new ones to maintain effective and compliant ways of working. We have identified several key issues that all housing providers should consider.
Protocol Compliance
Housing providers will continue to receive new disrepair claims. Throughout the disruption caused by coronavirus, landlords will still be expected to respond to these claims and comply with the Pre-Action Protocol for Housing Conditions Claims whilst doing so. We address the issue of disclosure in particular below.
Letters of claim will continue to be sent by post to your Registered Office, and the deadlines will run from the date of deemed service. Ensure you have systems to enable you to scan correspondence and forward it to the responsible officer who will handle the claim so deadlines are met.
Under the Protocol, the deadline for disclosure is 20 working days from deemed service of a letter of claim (2 working days after it is sent). So, for example, a letter dated 2 March 2020 would be deemed served on 4 March 2020 and disclosure would therefore be due by 1 April 2020. All housing providers must continue to comply with the Protocol and so landlords should begin preparing now.
Failure to meet deadlines often result in the issuing of further applications to court by tenant’s solicitors which in turn will lead to unnecessary costs orders against landlords.
Therefore, all records, particularly relating to customer contact and repair logs, should be held electronically. If required, this will allow for such documentation to be redacted for GDPR purposes remotely and disclosed to the tenant’s solicitor simply and efficiently.
Remember it is possible to request an extension to all Protocol deadlines and it is inevitable in these unusual times, this will need to be utilised, and should not be refused. Request extensions to deadlines at the earliest opportunity to enable an achievable timescale. It would be a difficult lawyer that would not agree to such a request.