Do you have to collectively consult for the minimum period of time before you can issue notice?
These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.
Related FAQs
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
With another lock-down in force in England, it has been confirmed that the courts will remain open. This is different to the first lockdown in March 2020, in which the majority of courts were closed and most face to face hearings did not take place. Hopefully, this new lock-down measure will ensure that cases are still being heard at a steady rate, and there should not be a backlog for your case to be dealt with.
Lord Chancellor Robert Buckland QC MP emphasised the importance of maintaining safety during the new measures: “Our courts & tribunals continue to be an essential public service, served by essential workers and meeting Covid-secure standards endorsed by public health officials. With the use of remote hearings wherever appropriate, this vital work can and should continue.”
A large sum of £110m has been spent in recent months to make courts safe and to ensure that trials should go ahead where necessary. As a result of the expenditure, hearings can now still take place both in person, whilst adhering to the rules, as well as remotely. Your case may be heard in court if it is deemed as being “necessary in the interest of justice”.
Precautionary measures, such as social distancing, will still be in place, with Judges and magistrates ensuring that this happens.
Lord Chief Justice, Lord Burnett of Maldon commented: “The next few weeks will present difficulties in all jurisdictions. But as before judges, magistrates, staff, the legal profession and others involved in the system will meet them and ensure that the administration of justice continues to function in the public interest.”
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The Thriving at Work Report and the recent NICE Workplace Mental Health Guidelines provide a good baseline for what all organisations should be doing on workplace mental health – this includes some guidance on training. There does need to be a plan in place and we recommend taking a holistic view of the integration of mental health first aiders into a business – ie it should be one component in a strategy that also comprises training for line managers, awareness training and education for all staff, peer support, and a documented framework for support and signposting. It is also worth ensuring you have senior manager sponsorship, strong links with Occupational Health if available and also raising awareness via any works councils or employee forums helps ensure there is buy in at all levels.