Skip to content

Do the usual publicity requirements for planning applications still apply?

The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.

Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.

A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.

The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.

The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.

The regulations are currently due to expire on 31 December 2020.

Related FAQs

How do I apply for an extension to Companies House?

The application is made via the Companies House website, and only takes a few minutes to complete. Companies House have indicated that the extension is “automatic and immediate” and will be for three months.

Having said that the extension is “automatic”, their website also says that Companies that have already extended their filing deadline, or shortened their accounting reference period, may not be eligible for an extension.

If an extension is granted, it will not affect the due date for filing accounts in future years – so the deadline will revert to the usual date for the next accounting period.

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

Does a sponsor need to report a change in workplace if a Tier 2 visa holder is working from home as a result of Covid-19?

No. The Home Office has confirmed that sponsors do not need to report sponsored workers as working from home, where this is directly related to the coronavirus outbreak.

However any UK employers who sponsor overseas workers, should also ensure that they remain compliant with their other sponsor licence duties, which includes reporting any change to an employee’s salary and duties.