Do leaseholders who have more than three properties in the UK have to pay the full contribution for building safety works and is there a way of finding out how many properties out leaseholders have in the UK?
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
Related FAQs
As discussed above, Covid-19 will inevitably deplete the workforce of housing providers in the foreseeable future. It would be prudent to consider making short-term policy changes to deal with this situation and manage the expectations of tenants going forward. A key policy change to consider is the extension of the standard lead-time for completing all non-urgent repairs and inform tenants of this change.
Such a change will also reduce pressure on landlords and front-facing staff.
As above, employers must protect the interests of their staff, particularly regarding health and safety. Extra care should be exercised when assessing the level of emergency of a repair on a case by case basis. All efforts should be made to reduce the number of attendances at properties by repair staff, whilst keeping all tenants safe.
As ever, communication is key – the pandemic cannot be used as a blanket excuse for abstaining from all duties and obligations. Housing providers must take a pragmatic approach in safeguarding customers whilst considering the interests of is workers. Maintaining lines of communication with all parties remains paramount.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
The CMA is particularly concerned about certain activities, its guidance highlights:
- Exchange of commercially sensitive information where this is not necessary in response to the crisis
- Collaboration which unfairly excludes third parties
- Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
- Seeking to maintain prices or prevent reductions in prices
- Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
Changing to shift working may give employers the opportunity to change hours / pay whilst also focusing work when it is needed. Like the other provisions, this should be done fairly, either across the board or by selecting teams/individuals based on objective business reasons. Imposing without agreement would create significant risk, therefore would require fair selection and consultation.