Skip to content

Do I need Planning Permission to change the use of a warehouse or factory unit to a temporary mortuary?

Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.

Sui generis uses are not within any Use Class. Consequently planning permission is required for the:

  • Change in the use to a sui generis use
  • Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class

Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.

Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/

Depending on the form of the enforcement action, there could be a right of appeal.

Related FAQs

What is the amendment to The Working Time legislation called?

The government introduced The Working Time (Coronavirus) (Amendment) Regulations 2020 to amend the Working Time Regulations 1998 to allow for the change.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
How do you prevent MHFA from handling situations that are for qualified individuals such as their GP or EAP?

The MHFA training makes this clear, it should be made clear in the MHFA role specification and procedures and discussed during regular MHFA peer support and MHFA surgery sessions. It is important to ensure that where an Employee Assistance Programme is in place, all MHFAs have details of that scheme available so they are able to instantly share details of the scheme with those who require support. If in doubt due to serious concerns then using 999 or Samaritans is an option.

How often do MHFA qualifications need updating?

The recommendation is every 3 years, however it is recommended that MHFAs receive regular ongoing training and support.