Can you still have people on furlough leave full-time after 1 July 2020?
Yes. You can continue to fully furlough employees until 30 September 2021 (but from between 1 August 2020 and 31 December 2020 and from 1 July 2021 you need to contribute to the cost). If on full-time furlough, employees continue not to be able to undertake any work for you. As before, they can undertake training, or volunteer or work for another employer or organisation (if contractually allowed).
Related FAQs
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
The current position is that the PSC is responsible for assessing whether IR35 applies. This current regime has been difficult to police by HMRC and HMRC considers there is widespread flouting of the rules by contractors.
From April 2021 the responsibility for assessing whether IR35 applies will shift to the end user/client (with the exception of ‘small’ companies) which will require an assessment to be carried out on a contract by contract basis. HMRC anticipates that this will be easier to monitor and that end user businesses will be more compliant.
The reformed regime will apply to payments made on or after 6 April 2021 for services carried out on or after this date.
CMA guidance suggests that it will not take enforcement action in respect of agreements which:
- Are appropriate and necessary to avoid a shortage, or ensure security, of supply
- Are clearly in the public interest
- Contribute to the benefit or wellbeing of consumers
- Deal with critical issues that arise as a result of the Covid-19 pandemic
- Last no longer than is necessary to deal with these critical issues
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.
The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .
The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.
Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.
The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.