Skip to content

Can you still have people on furlough leave full-time after 1 July 2020?

Yes. You can continue to fully furlough employees until 30 September 2021 (but from between 1 August 2020 and 31 December 2020 and from 1 July 2021 you need to contribute to the cost). If on full-time furlough, employees continue not to be able to undertake any work for you. As before, they can undertake training, or volunteer or work for another employer or organisation (if contractually allowed).

Related FAQs

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

In a situation where a building has a B1 EWS1 rating but the insurance companies are either refusing to quote or saying the cladding is a fire risk (due to the result of the intrusive survey for the EWS1 rating) and quadrupling insurance premium, is there anything that will help with this situation in the Building Safety Act or the secondary regulations when they come in or do you think it is something case law will have to address?

The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.

How should we deal with existing petitions already presented at court prior to 27 April?

You should speak to your advisors. We do not know presently how existing petitions will be dealt with by the Court. We do know that if any winding up order is made (based on a petition presented after 27 April), it could be found to be void and a creditor may face challenges. Even for petitions presented before 27th April, there is a risk that the Court will not be keen to make a winding up order so it is important that you look at the facts of your debt and weigh up all of the factors before deciding how to proceed.

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
What is the guidance in relation to the Mental Capacity Act 2005 and Deprivation of Liberty Safeguards during the Covid-19 pandemic?

The Department of Health & Social Care has published guidance for hospitals, care homes and supervisory bodies on the Mental Capacity Act 2005 (MCA) and Deprivation of Liberty Safeguards (DoLS) during the coronavirus pandemic.

In many scenarios created or affected by the pandemic, decision makers in hospitals and care homes will need to decide:

  • if new arrangements constitute a ‘deprivation of liberty’ (most will not), and
  • if the new measures do amount to a deprivation of liberty, whether a new DoLS authorisation will be required (in most cases it will not be).

If a new authorisation is required, decision makers should follow their usual DoLS processes, including those for urgent authorisations.

A summary of the key points to be taken from the guidance is outlined below:

Use of the MCA and DoLS due to Covid-19

  • During the pandemic, the principles of the MCA and the safeguards provided by DoLS still apply.
  • It may be necessary to change the usual care and treatment arrangements, for example to provide treatment for people with Covid-19, to move them to a new hospital or care home to better utilise resources or to protect them from becoming infected.
  • All decision makers are responsible for implementing the emergency Government health advice  and any decision made under the MCA must be made in relation to a particular individual, it cannot be made in relation to groups of people.

Best interest decisions

  • In many cases, a best interests decision will be sufficient to provide the necessary care and treatment for a person who lacks the capacity to consent to the care and/or treatment arrangements during this emergency period.
  • If an individual has made a valid and applicable advance decision to refuse the treatment in question, then the relevant treatment, even for Covid-19, cannot be provided.

Delivering life-saving treatment

  • Where life-saving treatment is being provided in care homes or hospitals, including for the treatment of Covid-19, then the person will not be deprived of liberty as long as the treatment is the same as would normally be given to any person without a mental disorder.
  • The DoLS will therefore not apply to the vast majority of patients who need life-saving treatment who lack the mental capacity to consent to that treatment, including treatment to prevent the deterioration of a person with Covid-19.

The full guidance can be found here.