Can we require employees to have their temperatures taken on the way in to work, and is this something we should be doing?
If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.
Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.
Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.
Large scale temperature checks have in some businesses become part of the “new normal” working environment.
Related FAQs
Changing to shift working may give employers the opportunity to change hours / pay whilst also focusing work when it is needed. Like the other provisions, this should be done fairly, either across the board or by selecting teams/individuals based on objective business reasons. Imposing without agreement would create significant risk, therefore would require fair selection and consultation.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
On 18 April 2020, it was announced that an exception to the current stay in possession proceedings and ban on all evictions has been made to allow possession orders to be made against trespassers.
This means land owners can take action to remove unauthorised persons occupying their land. Trespassers include: squatters; travellers; failed successors of secure tenancies; and licensees whose licences have been terminated.
Further, the automatic stay to possession proceedings currently imposed no longer applies to applications for interim possession orders meaning any persons found to be “squatting” on land without permission may again be subject to an order requiring them to leave your premises within 24 hours of service of that order.
HM Treasury have no current plans to pause the collection of apprenticeship levy payments from employers, therefore levy-paying employers must continue to make payments. There is also no plan to extend the 24 month period allowed to spend levy funds.