Can we require employees to have their temperatures taken on the way in to work, and is this something we should be doing?
If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.
Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.
Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.
Large scale temperature checks have in some businesses become part of the “new normal” working environment.
Related FAQs
Failure to comply with the collective inform and consult obligations could impact on the fairness of any dismissals – see next question. In addition, a Tribunal can award a protective award of up to 90 days gross pay for each affected employee. The purpose is intended punish the employer for not complying with the obligations, not to compensate the employee for their individual financial loss.
That will depend on the terms of your facility and the stance taken by your bank.
Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).
The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.
Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.
Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.
Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.