Can we apply for a loan under the CBILS?
If you are running a business, yes you can. Please see our Funding and Finance FAQ’s.
We are hearing that Banks are more likely to advance monies on the basis of known income, so for example notified legacies, where there may be a time lag in them being received or against investments where, if they were realised now, would crystallise a loss. Asking for a loan which will need to repaid from future services or trading income should be carefully considered in particular where the charity does not operate to create a surplus which would allow this.
Related FAQs
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The GMC recognises the challenges the doctors may face as the situation continues to develop. This includes concerns about the risks to the health of the doctors when treating patients with coronavirus. Doctors should follow the current public health advice including self-isolating if they know or suspect that they are infected or are at a higher risk of infection.
Finally, all necessary steps should be taken to ensure that doctors have access to protective equipment and minimise the risk of transmission when treating patients. It is imperative that a record is kept of all decisions made and how any safety or health concerns have been handled.
The GMC continues to work with NHS England and UK’s Chief Medical Officers to provide updates and advice to all doctors as the situation develops. Click here for more information.