Skip to content

Can the apprentice take a break or pause in learning due to coronavirus?

A break or pause in learning can be initiated where the interruption to learning due to Covid-19 is greater than four weeks. This must be reported as a formal break in learning. In such circumstance the funding to the training provider will be suspended for the duration of the break. Previously, the rules only allowed an apprentice to initiate this break in learning but this has been expanded to give employers and training providers the right to initiate this. Training providers should continue with their monthly IRL submissions to the ESFA. During breaks in apprenticeships it is not necessary for the apprentice to comply with the minimum of 20% on the job training requirement but this will resume when the break ends.

Related FAQs

How do I remain compliant and cover any risk?

Data on properties, and people, has never been more important.

Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.

It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.

Operatives need to be provided with the tools to operate in as safe a way as possible:

  • Checklist of questions to ascertain occupant’s current health
  • Protective equipment (masks, gloves, over clothing)

The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision
Can I make a claim under my cancellations/abandonment insurance?

Cancellation insurance usually covers certain expenses and loss of profit, as long as the reason for cancellation is not excluded. These exclusion clauses are often quite wide and exclude avian, swine flu, quarantine, and restrictions of movement as a result of communicable disease. This means that you may not be entitled to compensation under this cover.

What is my legal position if emergency legislation to tackle the outbreak makes performance of a contract illegal or impossible?

As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.

These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.

This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?

For example:

  • If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
  • If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible