Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
On 4 May 2020, the Government launched the Bounce Back Loan Scheme (BBLS), which is intended to cut red tape to enable smaller businesses to access finance quickly during the coronavirus outbreak.
The scheme helps small and medium-sized businesses to borrow between £2,000 and up to 25% of their turnover. The maximum loan available is £50,000.
The government guarantees 100% of the loan and there are no any fees or interest to pay for the first 12 months. After 12 months the interest rate will be 2.5% a year.
The length of the loan is 6 years, but it can be repaid early without penalty. No repayments will be due during the first 12 months.
Under the scheme, lenders are not permitted to take any form of personal guarantee or take recovery action over a borrower’s personal assets (such as their main home or personal vehicle).
Businesses can apply for a BBLS loan if it:
- is based in the UK
- was established before 1 March 2020, and
- has been adversely impacted by the coronavirus.
Any business regarded as being a business in difficulty on 31 December 2019 will need to confirm that it is complying with additional state aid restrictions.
Businesses from any sector can apply, except the following:
- banks, insurers and reinsurers (but not insurance brokers)
- public-sector bodies, and
- state-funded primary and secondary schools.
Businesses already claiming under the following schemes cannot apply although it is possible to convert an existing loan under such schemes into BBLS:
- Coronavirus Business Interruption Loan Scheme (CBILS)
- Coronavirus Large Business Interruption Loan Scheme (CLBILS)
- COVID-19 Corporate Financing Facility.
There are 11 lenders participating in the scheme including many of the main retail banks, which are listed on the British Business Bank’s website (www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-schemes/bounce-back-loans/for-businesses-and-advisors/). Applicants are directed to approach a suitable lender via the lender’s website. If an applicant is declined by a lender, they can apply to other lenders in the scheme.
The lender will ask applicants to fill in a short online application form and self-declare that they are eligible. All lending decisions remain fully delegated to the accredited lenders.
The Chancellor announced that employers will be given £2,000 to employ apprentices and £1,500 for apprentices over the age of 25 for each apprentice they hire from 1 August 2020 to 31 January 2021. These payments will be in addition to the existing £1,000 payment the Government already provide for new 16-18 year old apprentices.
He also announced that employers would be given £1,000 for taking on trainees in response to the traineeship scheme being extended.
The financial implications of having to repay all deposits and advance payments could be very serious for some businesses. As an alternative to a refund, many are offering customers the opportunity to re-book at a later date, or a voucher that can be redeemed against a subsequent booking.
The CMA’s view on this practice is that consumers can in many situations be offered alternatives of this type, but they should not be “misled or pressured” into accepting this. Their view is that a refund should be an option that is just as clearly and easily available. The CMA also points out that any restrictions that apply to credits, vouchers, re-booking or re-scheduling, such as the period in which credits must be used or services re-booked, must also be fair and made clear to consumers.
The full CMA guidance re “The Coronavirus (Covid-19) pandemic, consumer contracts, cancellation and refunds” can be found here.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
Commercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.