Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Related FAQs

In a situation where a building has a B1 EWS1 rating but the insurance companies are either refusing to quote or saying the cladding is a fire risk (due to the result of the intrusive survey for the EWS1 rating) and quadrupling insurance premium, is there anything that will help with this situation in the Building Safety Act or the secondary regulations when they come in or do you think it is something case law will have to address?

The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.

What was the eligibility criteria for the Government’s self-employment income support scheme?

You will be eligible if you are a self-employed individual or a member of a partnership and you:

  • have trading profits of up to £50,000
  • earn the majority of your income from self-employment
  • have submitted a Tax Return for 2019
  • have traded in the tax year 2019/20
  • are trading when you apply for a grant, or would be except for Covid-19
  • intend to continue to trade in the tax year 2020/2021
  • have lost trading/partnership profits due to Covid-19

 

Do employers still have to enrol and reenrol employees?
  • Yes, and this includes furloughed employees under the Coronavirus Job Retention Scheme.
  • Employers must continue to assess their new employees or newly eligible existing employees and enrol them where required, but can make use of the statutory postponement procedure which allows them to delay for up to three months the assessment of new employees for the purpose of enrolment (see further details here on the Pensions Regulator’s website). Declarations of compliance for new employers must still be completed in the normal way.
  • Postponement cannot be used for re-enrolment. The Regulator recommends employers use the re-enrolment date tool on the Regulator’s website to choose a date up to three months after the third anniversary of enrolment to assess staff for re-enrolment. Further information about employers’ obligations about reenrolment from the Pensions Regulator can be found here. Re-declarations of compliance for new employers must still be completed in the normal way.
VIDEO: An update from cashflow.co.uk expert Chris Silverwood about access to finance

Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.

Sections of the video and their timings are as follows:

(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)

(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II

(05.36) – bounce back loans have been a distraction

(06.27) – muted impact of fintech CBILS lenders

(07.52) – discussion about invoice discounting

(11.59) – looming insolvency environment

(12:52) – emerging themes

 

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.