Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Related FAQs

Can I still have my domestic gas appliances tested during the coronavirus outbreak?

Yes. The Health and Safety Executive has stated (as quoted from the Gas safe register site):

“Landlords have a legal duty to repair and maintain gas pipework, flues and appliances in a safe condition, to ensure an annual gas safety check on each appliance and flue, and to keep a record of each safety check.

“If you anticipate difficulties in gaining access as the Covid-19 situation progresses, you have the flexibility to carry out annual gas safety checks two months before the deadline date. Landlords can have the annual gas safety checks at their properties carried out any time from 10 to 12 calendar months after the previous check and still retain the original deadline date as if the check had been carried out exactly 12 months after the previous check.

“You are encouraged to arrange your annual gas safety checks as early as possible, as a contingency against tenants being in self-isolation for 14 days (in line with current guidelines), or gas engineers being unavailable due to illness. The two-month period to carry out annual gas safety checks should provide adequate resilience in most situations.

“In the event you are unable to gain access to the property, e.g. persistent refusal of access due to vulnerable tenants self-isolating, you will be expected to be able to demonstrate that you took reasonable steps to comply with the law, and that you are seeking to arrange the safety check as soon as all parties are able. This will need to include records of communication with the tenant, and details of your engineers attempts to gain access.”

Many Registered Providers have been suspending all gas and electrical testing where internal access is required, continuing checks in communal areas and are carrying out emergency repairs only, whilst void works are suspended and staff are working from home. This does not comply with the legislation, or the guidance.

What payments can be included in the claim for a grant?

You can claim for regular payments you are obliged to pay staff such as non-discretionary overtime, non-discretionary fees, non-discretionary commission and piece-time payments. Overtime in this context is referred to as ‘past overtime’ in the updated guidance which would suggest that you should use the variable pay calculation (see FAQ above) for those who regularly carry out overtime.

What rules has the European Commission introduced?

The Commission has provided guidance as to measures which Member States can introduce without notification. These include:

  • Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
  • Measures providing support direct to consumers
  • Measures which are already exempt from the notification requirement (discussed further below).

To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:

  • The provision of guarantees (including guarantees for 100% of loans)
  • The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
  • Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
  • Measures to recapitalise businesses
  • Measures to assist sectors hit particularly hard by the current crisis (eg transport)
  • Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus

The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.

What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.

What is my legal position if emergency legislation to tackle the outbreak makes performance of a contract illegal or impossible?

As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.

These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.

This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?

For example:

  • If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
  • If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible