Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
Schools should be considering both Youth MHFA training and Adults MHFA training so that there are people within every school who have the skills and knowledge to support the mental health needs of students and teaching staff.
After 25 March 2020, and until 30 September 2020, a landlord can only start possession proceedings against a tenant if they have served 3 months’ notice upon the tenant – irrespective of any grounds relied upon.
On 27 March 2020, the Court introduced new rules to put all possession proceedings (except against trespassers) on hold until 25 June 2020 – it means that the Court cannot make an order for possession or any other order that would cause someone to be evicted during that time.
These rules do not just apply to tenants who have fallen into rent arrears.
On 5 June 2020, the Government announced that this stay would be extended further until 23 August 2020.
This means that you can issue new possession proceedings (provided you have complied with the new temporary rules in relation to notice periods, if the notice was served since 25 March 2020) and you can continue with existing possession proceedings.
However, any progress you may be able to make in dealing with those proceedings is likely to be very limited – the Court will allow you to comply with directions orders that have already been made but non-compliance will not be punished (at least for the time being).
These rules, and the latest announcements, are in keeping with the Government’s expectation that landlords show compassion towards affected tenants and that all parties will work together to establish a suitable repayment plan to allow tenants to repay the arrears at an affordable rate.
Employees on any type of employment contract including full-time, part-time, agency, flexible or zero hours and foreign nationals who are eligible to work in the UK on any visa can be furloughed subject to the following excluded categories:
- Anyone who was not employed prior to 30 October 2020
- Anyone for whom you haven’t made a PAYE Real Time Information submission to HMRC between 20 March 2020 and 30 October 2020.
- Employees who are working but on reduced hours or for reduced pay
- Employees currently receiving SSP (see FAQ on SSP and self-isolation below)
- Public sector employees
- Employees of businesses or organisations in receipt of public funding for staff costs (except for those who are not primarily funded by the government and whose staff cannot be redeployed to assist with the Covid-19 response)
The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision