Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
There has been a significant amount of press coverage talking about institutional racism within the NHS not only in terms of the treatment of patients but also in terms of the low representation of ethnic minority staff in management positions. Whilst tackling that issue is beyond the brief here, it is important to recognise that sub conscious bias can, regrettably, play a part in decision making processes. An Employment Tribunal will explore a alleged discriminator’s conscious and sub conscious decision making and working in an environment which has not set out sufficient controls to avoid such sub conscious stereotyping places someone at a greater risk of being discriminated against.
In the context of the issues we are addressing here, i.e. risk assessments around BAME staff, as we have stated above, it is essential that BAME staff are represented at all levels in the discussion. Trusts need to be mindful that BAME are underrepresented in management positions.
BAME staff need to be included in the dialogue and need to have a safe place where they can challenge decisions that are being made in relation to them. There needs to be accountability in the processes applied. Meaningful conversations need to happen and concerns should not be dismissed.
Read more about thisThere are four criteria which must be satisfied if an agreement is to be considered exempt:
- It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
- It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
- It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
- It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).
The Vice President of the COP, Mr Justice Hayden, has issued guidance to assist parties during this challenging time.
The latest guidance with all relevant updates on developments is available on the judiciary website here.
Read more about thisPayments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Read more about thisIn our latest “in conversation” webinar we discussed the outlook for the corporate transaction market. Whilst it would be a brave person to predict the future of anything at the moment given current circumstances, we were joined by two organisations who are very well placed to provide their views.
John Laud, Head of Corporate Banking for North and West Yorkshire for Barclays, his colleague Stephen Loureda from their Credit Analysis Team, and Jill Williams, Investment Director of Mercia Asset Management’s Growth Fund, were in conversation with Ward Hadaway corporate partners Adrian Ballam and Jonathan Pollard to share their thoughts about how the ‘new normal’ for the transactions market may look:
- With supply chain and forecast prediction challenges, how will banks and investors determine what represents a sound opportunity?
- How will distressed and opportunistic acquisition opportunities be funded, and what is investor appetite for such opportunities?
- How have seller and buyer pricing expectations been impacted as a result of the pandemic?
- How are funders reacting, and how should ambitious businesses respond to the very low, or even negative, interest rates?
We expect this video to be of real value to those businesses whose plans of buying, selling or investment may have been impacted by the current economic crisis, but who are looking at opportunities to determine how they may shape their futures – #gettingbacktobusiness.
Read more about this