Skip to content

Can I progress an application for EIA development?

Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.

New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.

Related FAQs

What if you want to terminate the contract completely?

If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:

  • Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
  • A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all

If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.

Even if the right to terminate the contract does exist, there might be particular rules about the following:

  • How much notice has to be given
  • How such notice has to be served (for example, it might have to be in writing to a particular address)
  • When the notice can be served (perhaps on an anniversary of the start of the contract)
  • How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)

All of these factors must be taken into account, and any contractual processes for termination are followed.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Can the apprentice take a break or pause in learning due to coronavirus?

A break or pause in learning can be initiated where the interruption to learning due to Covid-19 is greater than four weeks. This must be reported as a formal break in learning. In such circumstance the funding to the training provider will be suspended for the duration of the break. Previously, the rules only allowed an apprentice to initiate this break in learning but this has been expanded to give employers and training providers the right to initiate this. Training providers should continue with their monthly IRL submissions to the ESFA. During breaks in apprenticeships it is not necessary for the apprentice to comply with the minimum of 20% on the job training requirement but this will resume when the break ends.

When does Flexible Furlough start?

The Flexible Furlough Scheme was introduced from 1 July 2020 and is due to come to an end on 30 September 2021.

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision