Can I progress an application for EIA development?
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
Related FAQs
All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.
- Working with PFI providers to get contingency plans up to date
- If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
- maintain unitary charge payments
- revise contract requirements/standards
moderating payment and performance regimes where appropriate.
- In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
- When putting local bespoke arrangements into place it is vital that:
- Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
- It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Yes, however holiday pay during furlough must remain at the normal rate of pay and not the reduced furloughed rate. You can still claim for this period under the scheme but you will be responsible for any amounts beyond the maximum you can claim. Employers have flexibility to restrict when leave can be taken both during and after period of furlough in the normal way.
If an employee usually works bank holidays then the employer can agree that this is included in the grant payment. If the employee usually takes the bank holiday as leave then you would either have to top up their usual holiday pay, or give the employee a day of holiday in lieu.
The best advice is that parties should proceed as they would have done before the crisis began.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.