Can I offer credits or re-booking as an alternative to a refund?

The financial implications of having to repay all deposits and advance payments could be very serious for some businesses. As an alternative to a refund, many are offering customers the opportunity to re-book at a later date, or a voucher that can be redeemed against a subsequent booking.

The CMA’s view on this practice is that consumers can in many situations be offered alternatives of this type, but they should not be “misled or pressured” into accepting this. Their view is that a refund should be an option that is just as clearly and easily available. The CMA also points out that any restrictions that apply to credits, vouchers, re-booking or re-scheduling, such as the period in which credits must be used or services re-booked, must also be fair and made clear to consumers.

The full CMA guidance re “The Coronavirus (Covid-19) pandemic, consumer contracts, cancellation and refunds” can be found here.

Related FAQs

VIDEO: Force majeure during the coronavirus pandemic

Commercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.

Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

I hold a licence but can’t trade. Can I terminate it?

A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.

Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.

What is the government guidance on making places of work as safe as possible to return to?

The government has produced a series of industry specific “Covid-19 Secure” guidelines, which employers should follow. These guidelines are designed to keep the risk of infection as low as possible, while allowing as many people as possible to resume their livelihoods.