Skip to content

Can I enact a rent suspension clause in my commercial lease?

Most rent suspension clauses in commercial property leases are unlikely to come to the assistance of the tenant. These clauses normally apply only where the premises has suffered substantial physical damage and are, as a consequence, incapable of being occupied, used or accessed. The coronavirus pandemic does not involve any physical damage to a property, loss from the crisis will be purely financial. Such losses then will not be covered by the landlord’s buildings insurance policy in a way that will allow a tenant to claim rent suspension.

Related FAQs

What does this mean for my business?

The guidance is helpful and is likely to be useful to businesses as they seek to respond to the crisis and to restart their business activities as lockdown is eased. However, there remain outstanding questions. For example, can collaboration to prevent widespread insolvencies be viewed as in the interest of consumers? Businesses need to remain aware of the extremely high stakes involved in relation to competition law. Businesses contemplating collaboration with competitors should take legal advice before doing so.

What about other Companies House filings?

The Bill allows the Secretary of State to make regulations to temporarily extend various filing date deadlines for companies. These include deadlines for filings accounts, confirmation statements, charges register, director and secretary appointments and resignations. The extended period must not exceed 42 days where the existing period is up to 21 days, or 12 months where the existing period is 3, 6 or 9 months.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Should Covid-19 be recorded as a cause of death?

The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.

If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation. 

In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.

Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.