Skip to content

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Related FAQs

Would it be appropriate to suspend someone who refuses to restrict their duties?

Suspension should always be a last resort and not a knee jerk reaction. We would not advise suspension unless a the above steps around the risk assessment have been undertaken. Depending on your local policies, suspension could then be an option on the basis that their health and safety and the health and safety of others are put at risk by their actions.

I’m a housing provider. How do I continue to manage disrepair during the coronavirus outbreak?

The practicalities and processes regarding disrepair claims will undoubtedly be affected. Housing providers will have to adopt a risk-based approach and consider government guidance to handle claims going forward. Key points to consider are:

  • Compliance with the Pre-Action Protocol for Housing Conditions Claims (particularly disclosure)
  • The practicalities of inspection
  • Non-urgent repairs
What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What should be included in genuinely self-employed contractor terms?

If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:

  • The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
  • The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
  • The contractor should have sufficient control over how, when and where (if possible) they provide the services;
  • A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task

We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.

What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.