Skip to content

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Related FAQs

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

If an employee has had a coronavirus test, can we require them to disclose evidence of their test results?

Obtaining an employee’s Covid-19 test result will amount to processing personal data for the purposes of the General Data Protection Regulation 2016/679 (GDPR) and information about an employee’s health is a special category of data (sensitive personal data under the Data Processing Act 2018 (DPA)).

In accordance with the GDPR and DPA, there must be lawful grounds for processing such information. Most employers rely on employees’ consent to obtain medical information and process sensitive personal data and if the employee is unwilling to give consent, you will not normally be entitled to the information.

Special category data can be processed lawfully if it is necessary for the performance of a task carried out in the public interest or in the exercise of official authority vested in the data controller. Employers may be able to require an employee to disclose their Covid-19 test if there is a substantial public interest, such as ensuring that the employee self-isolate if they have a positive test. However, there is a risk that this measure could be considered disproportionate particularly if it is enforced on all employees as a blanket measure.

What is the Clinical Negligence Scheme for Coronavirus?

The Government has recently passed the Coronavirus Act 2020 in a response to the challenges posed by the pandemic, especially in relation to those facing the NHS during this time of crisis.  NHS Resolution worked closely with the Department for Health and Social Care to draft a clause within the Coronavirus Act providing indemnity for clinical negligence for any coronavirus related activity not currently covered by an existing arrangement.  In order to implement this clause, NHS Resolution has launched the Clinical Negligence Scheme for Coronavirus (“CNSC”).

It is intended that the CNSC will cover new contracts put in place for healthcare arrangements to respond to coronavirus, such as organisations supporting testing arrangements or Independent Contractors making agreements with NHS England and NHS Improvement to release capacity to the NHS.  Membership is not required for this scheme and the contracts entered into will automatically provide indemnity under the scheme.

The CNSC will not replace existing indemnity provisions made under the Clinical Negligence Scheme for Trusts (“CNST”) and it has been confirmed that the new Nightingale Hospitals will be covered by CNST rather than CNSC.  Similarly, NHS Resolution have confirmed that those doctors and nurses returning to practice from retirement, or those joining as students will be covered by the CNST or, where applicable the Clinical Negligence Scheme for General Practice (“CNSGP”).  The CNSC will not cover returning midwives to the profession, but the Royal College of Midwives have confirmed that they will extend all of the benefits of membership including Medical Malpractice Insurance to returning retired midwives.

For more information regarding this please click here.

How should contracting authorities work with PFI providers?
  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Am I obliged to offer staff flexible furlough?

No, there is no obligation on employers to offer a flexible furlough arrangement to staff. Operationally, flexible furlough may not be appropriate for your business and equally, returning on a part-time basis may not be suitable for individuals already furloughed for various reasons. Concerns about returning to work part-time or at all should be considered on a case-by-case basis.