Skip to content

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Related FAQs

How can workers get to work safely?

The Government’s guidance says walk, cycle or drive to work and avoid public transport if you can. Businesses will need to support workers in adopting alternative travel methods to reduce exposure to the virus. You could consider staggering start and finish times for shifts to reduce commuting during peak hours, or support cycling with secure storage facilities and a drying room.

What are the new Procurement Policy Notes (PPN)?

The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.

PPN 01/20: Responding to COVID-19

The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.

This PPN provides guidance for the following circumstances:

  • Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
  • Direct award due to an absence of competition or protection of exclusive rights
  • Call off from an existing framework agreement or dynamic purchasing system
  • Call for competition using a standard procedure with accelerated timescales
  • Extending or modifying a contract during its term

PPN 02/20: Supplier relief due to COVID-19

PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.

This PPN provides guidance for the following circumstances:

  • Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
  • Put in place appropriate payment measure to support supplier cash flow
  • Where contract payments are based on ‘payment by results’ make payments based on previous invoices
  • Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
  • Ensure invoices submitted by suppliers are paid immediately on receipt

PPN 03/20: Use of Procurement Cards

The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.

This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:

  • Increase a single transaction limit to £20,000 for key card holders
  • Raise monthly limits on spending with procurement cards to £100,000 for key card holders
  • Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs

Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.

The PPN also advises that by 30 April 2020, in scope organisations should:

  • Ensure that a number of appropriate staff have the authority to use these cards
  • Open all relevant categories of spend to enable these cards to be used more widely
Are there any exceptions to the obligation to return deposits?

The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.

This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.

The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.

What do I do if my visa is due to expire but I can't travel?

If your visa has expired or will do before you are able to safely leave the UK, you can apply for “Exceptional Indemnity” by contacting the Coronavirus Immigration Team. You will need to provide evidence as to why you cannot leave, which could include a positive Covid-19 test or evidence of being unable to make travel arrangements to leave the UK in time.

You should note that “Exceptional Indemnity” does not extend your leave, but temporarily protects you from adverse action being made against you as result of overstaying your visa.

What impact does the Regulations have in respect of matters which arise from Fire Safety Audits - e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?
The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.