Skip to content

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Related FAQs

How does COVID-19 affect Right to Work checks?

All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.

Will site visits, hearings and inquiries still take place?

Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.

The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .

The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.

Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.

The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.

How should contracting authorities work with PFI providers?
  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Will the golden thread requirements in relation to maintaining a central record of building info be retrospective?

The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.

What measures are being implemented to protect residential property tenants?

On 18 March 2020, the Government announced that it would pass emergency legislation which would prevent landlords, both social and private, from bringing possession proceedings against tenants who are unable to pay their rent. The Housing Secretary, Robert Jenrick, stated that “no renter who has lost income due to coronavirus will be forced out of their home, nor will any landlord face unmanageable debts.”

The announcement came after several organisations, including housing charity Shelter, expressed concerns that more than 50,000 households could face possession proceedings due to the economic uncertainty following the Covid-19 outbreak.