Skip to content

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Related FAQs

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Are all employees required to stay at home?

No, where employees cannot work from home, and it is safe for them to return to work, they should do so.

How do I make arrangements for end point assessments for apprentices?

Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.

Understanding of the extent of the Covid-19 risk to BAME colleagues is evolving – what does that mean for NHS employers?

In practice this means that any risk assessment will need to be reviewed constantly and adjusted as our understanding of the nature and level of the risk grows.

Some service-providers are instigating special Oversight Groups to keep this issue under review but engagement and consultation with those affected is critical and making sure they feel confident to raise concerns and refuse to work if they believe they are not safe.

What happens if a patient is admitted to critical care during the pandemic?
  • On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
  • A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.