Can I argue that my contract has been frustrated?
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
No. Before continuing any negotiations, you need to strongly consider whether now is the best time to settle. There is a myriad of uncertainty due to the pandemic, with unemployment rates increasing, volatility in the stock markets and difficulties regarding placing valuations on assets. This could all lead to the financial settlement being unfair to you and cause you financial difficulties in the future.
Any financial settlements reached following marital separation should be embodied in to a Court Order, to prevent future claims from your ex-spouse. As a general principle, although maintenance orders are always variable, financial orders in respect of capital (e.g. house, cash, investments, pensions) are final and it is very difficult to set aside a Court Order. The question will be whether or not the pandemic is judged as a Barder event, which broadly means something viewed as unforeseen. It would be challenging for you to argue that the effects of COVID-19 are unforeseen given the widespread expectation of an economic crisis. The Court previously found against a husband who wanted to revisit an Order that he said was unaffordable following the 2008 financial crisis, with one Judge commenting that a 90% drop in the Husband’s share price was a “natural process of price fluctuation”.
Even if you informally agree a settlement with your ex-spouse, and you do not have this reflected in a Court Order, your ex-spouse may still rely on this agreement within future Court proceedings and argue that you should be held to it.
It is, therefore, very dangerous to be reaching any financial settlements at this time with your ex-spouse without careful consideration and legal advice. Further, even if an agreement is reached, market volatility can mean longer implementation times, especially when a settlement relies on the sale of property.
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
We have developed a toolkit to assist with compliance. The Toolkit contains a specimen contract; detailed guidance; step by step guides and flowcharts; details of the factors to take into account for the status determination test; procedures for challenging the determination; and standard letters for the process. Click here to fill in a form and register your interest in the Toolkit, which contains:
- Detailed guidance in the form of Key Facts
- Employment status checklist
- Employment status assessment flowchart
- Status questionnaire and guidance
- Letter confirming self-employed status (agency)
- Letter confirming employed status (agency)
- Letter confirming self-employed status (direct with PSC)
- Letter confirming employed status (direct with PSC)
- Status disagreement process guidance
- Status disagreement process flowchart
- Letter confirming outcome of status disagreement process
- Consultancy agreement
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.