Can I argue that my contract has been frustrated?
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Related FAQs
The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.
If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.
Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.
If you don’t want to make redundancies, or if you can’t reduce employee resource, either in a particular department or across the workforce as a whole, then you need to think about alternatives to redundancy.
Equally, you may want to flex the resource you have available to you – without making drastic changes. For example you may want to consider:
- unpaid leave and sabbaticals
- retraining and redeploying
- forcing annual leave
- flexible working
- capability issues
- lay off
- short time working
- reductions in salary
- reductions in working hours
- changing to shift working
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Local government legislation formerly stipulated that councillors must be physically present to vote and this requirement has already led to the widespread cancellation of Council meetings. There is a limit to what can be achieved under the chair’s emergency powers and delegation to officers.
The Government has now legislated to allow for remote voting until 7 May 2021. The secondary legislation required was issued in draft on 2 April and has been in force since Saturday 4 April.
The legislation allows for committee meetings to go ahead where members and any members of the public attending remotely can all times “hear (and where possible see) and be heard (and where possible be seen) by the other members in attendance”.
It remains to be seen how many local authorities take up the opportunity to hold a virtual committee meeting. Concern has been expressed that the demographic of local councillors may mean that members have difficulty with the technological mechanisms for holding such meetings. However, the message from the Secretary of State is clear that wherever possible, the planning system should keep moving in these current times.
Yes.
Workers (and agency workers) who are aware of the requirement to self-isolate and are due to work during their isolation period at a place other than their designated place (see below) must, as soon as reasonably practicable and in any event before they are next due to start work within the isolation period, tell their employer that they are self-isolating, and set out the start and end dates of their isolation period.
Clear communication to all workers about their obligation to do this is strongly recommended.