Skip to content

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Should you rely upon Statutory Demands issued after 1 March to present a Winding Up petition?

No. No action need be taken in relation to the demand but we would advise against presentation of a petition based upon any Statutory Demand issued between 1 March 2020 and the end of the restrictions. As you may be aware, with Winding Up there is no requirement to issue a Statutory Demand notice before proceeding so this is unlikely to create too many issues – click here to see whether you should issue petitions on other grounds.

There is nothing to prevent statutory demands being served at this time. However, there may be limited benefit as it cannot form the basis of a future winding up petition.

What is the Government’s Coronavirus Job Retention Scheme?

All employers in the UK are eligible to participate in the scheme. The purpose of the scheme is to allow employers to claim back employment costs if they have furloughed employees arising from the coronavirus crisis. Importantly this means the scheme is not limited to cases where the employee would otherwise have been made redundant.

Key points:

  • Between 1 November 2020 – 30 June 2021, the government will reimburse employers for 80% of wage costs, up to a cap of £2,500 per month, with employers expected to contribute 10% of that 80% in July 2021 and 20% of that 80% in August and September 2021. Employers will still need to pay employer NICs and employer pension contributions (these cannot be claimed for).
  • The scheme now also allows employees to return to work part time being on furlough for the remainder. See flexible furlough above for more information.
  • The employer can agree to pay the employee more than it will be reimbursed but it cannot reclaim the additional amount or any other costs associated with the additional amount.
  • The workers covered by the scheme are those who have been “furloughed” which is a leave of absence.
  • Workers must be told about and agree to this change of status (see below).
  • Employers have to continue to pay the furloughed workers and the Government will reimburse the employer.
  • HMRC is administering the scheme and it has been extended until the end of September 2021
  • Those who left employment and are re-employed and subsequently furloughed by agreement are eligible (please see the FAQ regarding redundancy and furlough above).
  • Payments may be withheld if claims are based on inaccurate or dishonest information, or are found to be fraudulent. HMRC has put in place an online hotline for employees and the general public to report suspected fraudulent claims.
  • The Government has made alternative help available for employers to continue to pay employees while the scheme is set up.
Are benefits to be included in the claim for a grant?

You cannot include the following payments in a claim:

  • Discretionary bonus or commission payments
  • Tips
  • Non-cash payments
  • Non-monetary benefits including taxable benefits in kind
  • Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)

The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.