Skip to content

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

Related FAQs

What about office holders?

Office holders who provide services under an intermediary (such as a service company consultancy agreement) and whose services relate to the office held, would fall under the IR35 regime and must be assessed accordingly.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

What was the purpose of the Chancellor's economic update?

On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.

Do I have to continue to pay furloughed staff while furloughed? Can I wait until I receive the money from the government?

To qualify for a grant under the scheme you must pay your furloughed staff the wages you are claiming for. Failure to do so may result in a HMRC investigation and/or claims from furloughed staff for unlawful deductions from wages and possibly constructive dismissal claims.

Normal benefits including non-monetary benefits should continue during furlough unless the individual has agreed in writing to reduce or remove a benefit during this time.

Employers are expected to apply for one or more of the financial support schemes available to be able to continue to pay staff.