Skip to content

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

Related FAQs

What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

What will my case look like going forward and what are the courts doing?

During the Covid 19 crisis lawyers and the courts have had to adapt with hearings being heard remotely and with more electronic communication. It is clear that going forward, some of these changes will become more permanent.

The Lord Chancellor, Robert Buckland QC MP, has spoken last week regarding changes to the justice system following the COVID-19 pandemic and we know that there is a significant backlog of work that needs to be processed.

Firstly, 10 sites have been identified for ‘Nightingale courts’ which will allow for better social distancing. The authorities have suggested that it is a possibility that courts will need to stay open for a longer time or at weekends, to increase the number of cases that can be heard safely on any given day. This will enable more cases to be heard in a day and therefore a swifter outcome for your case. The standard of video technology will also continue to improve, with plans for new technology being rolled out across all courts form July onwards. The enhanced use of technology may result in matters being heard more efficiently, decreasing the time spent during each hearing.

HMCTS is working to expand access to audio and video technology to support more and new types of hearings. There has been an increase in the use of new and varying equipment over the lock-down period. With the appropriate systems in place, many more hearings could take place on platforms such as the Cloud Video Platform (CVP). Throughout July, the CVP will be more readily available to Country courts. There will be further hardware rolled out to improve the quality of video hearings, and there will be more efficient methods used to organise video lists.

The increased use and training of CVP means that witnesses and advocates may not need to attend court and could attend the hearing remotely. This will give you increased flexibility, enabling you to attend from your office or home. The CVP is efficient and simple to use, with no complex functions; making it user-friendly. This should make litigation more time and cost effective (albeit that there will be the cultural challenge of having less contact with your legal team or the court experience).

How do I determine contractor status?

You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.

Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.

The key factors used to determine status  are:

  • Control:
    • How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
  • Personal service:
    • Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
  • Mutuality of obligation:
    • Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?
Should my apprentice continue their training during the coronavirus outbreak, even if they’re furloughed?

The Government maintains that apprenticeships will be an important part in the economic recovery post-lockdown and therefore ESFA is encouraging training under apprenticeships to continue, even where an apprentice is furloughed, provided that the training does not provide services to or generate income for their employer. E-learning is being encouraged as a method of delivery.