Can I argue that my contract has been frustrated?
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Related FAQs
The CMA is particularly concerned about certain activities, its guidance highlights:
- Exchange of commercially sensitive information where this is not necessary in response to the crisis
- Collaboration which unfairly excludes third parties
- Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
- Seeking to maintain prices or prevent reductions in prices
- Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
After 25 March 2020, and until 30 September 2020, a landlord can only start possession proceedings against a tenant if they have served 3 months’ notice upon the tenant – irrespective of any grounds relied upon.
On 27 March 2020, the Court introduced new rules to put all possession proceedings (except against trespassers) on hold until 25 June 2020 – it means that the Court cannot make an order for possession or any other order that would cause someone to be evicted during that time.
These rules do not just apply to tenants who have fallen into rent arrears.
On 5 June 2020, the Government announced that this stay would be extended further until 23 August 2020.
This means that you can issue new possession proceedings (provided you have complied with the new temporary rules in relation to notice periods, if the notice was served since 25 March 2020) and you can continue with existing possession proceedings.
However, any progress you may be able to make in dealing with those proceedings is likely to be very limited – the Court will allow you to comply with directions orders that have already been made but non-compliance will not be punished (at least for the time being).
These rules, and the latest announcements, are in keeping with the Government’s expectation that landlords show compassion towards affected tenants and that all parties will work together to establish a suitable repayment plan to allow tenants to repay the arrears at an affordable rate.
The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The basics of health and safety law requires that employers take “all reasonably practicable steps” to ensure workers’ safety and that a suitable and sufficient assessment of risk is undertaken. It is the individual assessment of Covid-19 risk in each workplace that will be central. Employers will be required to conduct a robust risk assessment and then, following the hierarchy of controls, put robust processes and safeguards in place to address those risks.
UK government guidance and HSE advice is continually evolving, which in practice means that any risk assessment will need to be reviewed very regularly as that guidance develops. There is flexibility for individual businesses within the overall government framework and there will need to be a process of evaluation to ensure that the measures in place continue to meet the requirements.
The starting point of avoid, eliminate and control means looking at individuals continuing to work from home where possible (the fewer the number of people back in the workplace the lower the risk), and if not look at risk management, which leads to administrative controls – i.e. changing work practices before ending up at PPE. PPE is generally seen as control of last resort but in practice – facemasks, disposable gloves and constant prompts to wash hands for example.
In terms of changing working practices, employers should be thinking about:
- the workspace and how this is laid layout
- how do we make sure it is kept clean and hygienic
- how do we keep people apart
- how can we use toilets, canteens or other shared spaces/facilities safely
- how do we promote and enable higher levels of workplace hygiene
- if we are going to rely on PPE – can we get it, and is it suitable
- what about limiting customer interactions
- will there be enough first aiders on site
- can we manage fire safety, deliveries etc
- what about higher risk workers
- should work tools and equipment be allocated on an individual basis to employees.
These decisions need to be recorded and clearly communicated to staff members.