Skip to content

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?

Related FAQs

Which publicly funded organisations can consider furlough?

Some employers falling into the third group of organisations described above could understandably feel aggrieved that on the first reading of the guidance they are not able to furlough employees and rely on the Government scheme. Many publicly funded organisations that are not public sector employers, receive a package of public funding with little expectation on how that funding is used or applied, other than broadly for it to be used in providing the services it is contracted to deliver. Also, several publicly funded organisations have many different income streams and the element of funding that is received from the public purse can be only an element of their operating costs.

Unfortunately there is still no clear guidance on when employers falling into the third category identified above can use the scheme. The only reference in the guidance on this states that where organisations are not “primarily funded” from the public purse and whose staff cannot be redeployed to assist with the coronavirus response, the scheme might be appropriate to be used for some staff. This seems to suggest that where an employing organisation is not wholly or mainly funded by public funding and staff cannot be redeployed to work in areas in the effort to combat coronavirus, then it would be appropriate for the employer to access the scheme.

If considering applying for grants under the scheme a sensible approach would be to look at the combined total of your public funding and payments under the scheme and make sure it will not represent more than 100% of the level of total income you would have expected to receive during this period in a non-Covid scenario.

Local Authorities are expected to maintain support to suppliers and this should be considered:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/874178/PPN_02_20_Supplier_Relief_due_to_Covid19.pdf

What is happening with public transport?

Government guidance is that public transport should be avoided wherever possible. Transport providers will be expected to follow government guidance to make their services more COVID-19 secure.

How might the transition to a "new normal" impact on contracts?

The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.

This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.

For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?

Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.

Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What can suppliers of goods and services do to minimize risk?

If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.

If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract.  This will involve time and legal expense.