Can I apply a Force Majeure clause?
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Related FAQs
The Government has introduced legislation to expand the list of those who can register deaths to include Funeral Directors who are dealing with the funeral arrangements and who has been authorised by a relative of the deceased to register the death. Also, the medical cause of death certificate can be emailed to the Registrar’s office and arrangements made to have a telephone appointment to provide the Registrar with information to register the death. The requirement to attend the Registrar in person to sign the Register has been relaxed so that this is not necessary. It will however still be necessary to register the death within 5 days.
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Borrowers will not have to pay a guarantee fee. Lenders will pay a fee to access the scheme. The Government will make a Business Interruption Payment to cover the first 12 months of interest payments and any lender-levied fees, allowing smaller businesses to benefit from no upfront cost.
British Business Bank has indicated that following earlier discussions with the banking industry, some lenders indicated that they would not charge arrangement fees or early repayment charges to SMEs borrowing under the scheme. Each business should check the terms of the loans being made to ensure this is the case and what the interest rate and prepayment fees will be following the period in which the Government makes payment of these amounts.
Yes.
An employer which is aware that a worker or agency worker is or ought to be self-isolating, should not knowingly allow that worker or agency worker to leave the place that they are self-isolating in (“the designated place”). To do so without reasonable excuse would amount to an offence which could result in the employer being issued with a fixed penalty notice.
The value of the fixed penalty varies depending on if it is the first or subsequent fixed penalty notice to be issued:
| First fixed penalty notice | £1,000 |
| Second fixed penalty notice | £2,000 |
| Third fixed penalty notice | £4,000 |
| Fourth, and any subsequent fixed penalty notice | £10,000 |