Can I apply a Force Majeure clause?
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Partner at Ward Hadaway Adrian Ballam talks to corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) to explore the practical ins, outs, dos and don’ts of CBILS applications, answering the questions:
- How are banks making their assessments of whether a business can afford a CBILS loan when for many they cannot accurately forecast their revenues for at least the next three months?
- What are the red flags that banks are looking for when assessing whether or not to grant a request for a CBILS loan?
- What cost mitigation measures should a business have already implemented prior to applying for a CBILS loan?
- What level of information should a business provide to support a CBILS application?
- What common mistakes are businesses making when applying for funding?
- What general tips do you have for businesses seeking CBILS funding?
Click read more to view the video.
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
The Office of the Public Guardian is continuing to accept applications to register Lasting Powers of Attorney but their usual estimated timescale of eight to ten weeks is likely to be affected by the current situation.
Consequently, an alternative or interim measure if you need something quickly is to execute a General Power of Attorney to authorise someone to act as your Attorney to undertake day to day financial transactions for you. The General Power of Appointment only needs to be executed by you in the presence of a witness (not the Attorney) to be valid and does not need to be registered with the Court of Protection. However, the Power of Attorney would cease to have effect if you become incapable of managing your affairs. It should be seen as a stop-gap only.