Can I apply a Force Majeure clause?
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Related FAQs
The General Medical Council (GMC) have published guidance online for doctors during this time of uncertainty.
Alongside this, their website displays guidance for temporary registration to approximately 15,000 doctors, who left the register or gave up their licence to practise in the last three years.
These clinicians have been contacted to assist with the growing pandemic, outlining the process they would follow and informing them of their right to opt-out. The Secretary of State for Health can ask the GMC to grant such registration under Section 18a of the Medical Act 1983, in an emergency.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
The Government has produced workplace guidance for employers, setting out 2 key messages for employers:
- Continue to make workplaces as safe as possible; and
- Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate
Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
As long as you can demonstrate that you have exercised reasonable care in determining status you have discharged your obligations in that respect. However, if you are unable to demonstrate this, you may as the end user client be responsible for the contractor’s tax and NIC’s.