Skip to content

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?

Related FAQs

What should I do if I have a hearing scheduled in the COP?

Parties are encouraged to review upcoming matters to assess the viability for there to be any agreement which can be reached in relation to the issues in dispute or to consider whether the case needs to proceed to a remote hearing. If directions or issues can be agreed between the parties, reducing the need for remote hearings, then that is the preferred option.

How should I approach negotiations with my landlord?

Given the impact the Coronavirus is going to have upon the commercial property market, landlords will undoubtedly, as a matter of good commercial sense, will have to seriously entertain approaches from tenants seeking a rent suspension – notwithstanding there is no entitlement to the same under their lease.

Some landlords may decide it is better to waive or suspend rental payments over the short term rather than face their tenants going out of business and leaving them with an empty building in a flat or dead market.

A measure falling short of a rent suspension would be for the tenants to negotiate with their landlord’s monthly payments of rent rather than quarterly and for those monthly payments to be in payments arrears, rather than in advance.

What if we are a charity in Scotland Wales or Northern Ireland?

Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland.  In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:

  • £30 million for the Scottish Government
  • £20 million for Welsh Government
  • £10 million for the Northern Ireland Executive

There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.

Can I be investigated or prosecuted by HSE if one of my workers contracts Covid-19?

The reality of these unprecedented times is that enforcement of health and safety legislation by the HSE (particularly through the criminal courts) in relation to Covid-19 is an extremely unlikely outcome.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.