Can I apply a Force Majeure clause?
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Related FAQs
Yes.
Workers (and agency workers) who are aware of the requirement to self-isolate and are due to work during their isolation period at a place other than their designated place (see below) must, as soon as reasonably practicable and in any event before they are next due to start work within the isolation period, tell their employer that they are self-isolating, and set out the start and end dates of their isolation period.
Clear communication to all workers about their obligation to do this is strongly recommended.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.
If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.