Skip to content

Can I amend my divorce settlement due to Covid?

Maintenance Orders are capable of variation so if your income has reduced as a result of the pandemic, you may be entitled to reduce your payments. You should ensure that any reduction is reflected in a Court Order to ensure your ex-spouse cannot claim arrears from you.

It is not generally possible to vary capital and pension settlements included in Court Orders unless there has been a significant event, sometimes known as a “barder event”. The following four conditions must be satisfied:

  1. New events have occurred since the Order which invalidate the basis or fundamental assumption on which the Court Order was made and which were unforeseen and unforeseeable. This can include a change in the value of assets, employment status, inheritance and death.
  2. The new events occurred within a relatively short time of the Order being made.
  3. The Application to change the Order is made reasonably promptly.
  4. If the Application succeeded, this would not prejudice any third parties who have acquired assets in good faith e.g. if the family home has already been sold to a third party.

The applications relying on Covid as a significant event have had limited success. The circumstances in which the Barder principle may apply are few and far between. It is of note that the global financial crisis of 2007/2008 was not considered to be a Barder event.

Care should, therefore, be taken when deciding whether to pursue a change to the Divorce settlement and it is recommended that you speak to a specialist Family Law team like ours.

Related FAQs

How long do I have to bring a claim?

Anybody who wishes to make a claim for provision under the 1975 Act must be issue their claim at court within 6 months of the Grant of Probate being issued in the deceased’s estate.

This does mean that it is quite important to act quickly if you believe that you may wish to bring a claim under the 1975 Act against an estate.  Whilst it is possible to make an application for financial provision more than 6 months after the issue of the Grant of Probate, the court would need to be satisfied with the reasons which are provided for the delay.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

What is the Clinical Negligence Scheme for Coronavirus?

The Government has recently passed the Coronavirus Act 2020 in a response to the challenges posed by the pandemic, especially in relation to those facing the NHS during this time of crisis.  NHS Resolution worked closely with the Department for Health and Social Care to draft a clause within the Coronavirus Act providing indemnity for clinical negligence for any coronavirus related activity not currently covered by an existing arrangement.  In order to implement this clause, NHS Resolution has launched the Clinical Negligence Scheme for Coronavirus (“CNSC”).

It is intended that the CNSC will cover new contracts put in place for healthcare arrangements to respond to coronavirus, such as organisations supporting testing arrangements or Independent Contractors making agreements with NHS England and NHS Improvement to release capacity to the NHS.  Membership is not required for this scheme and the contracts entered into will automatically provide indemnity under the scheme.

The CNSC will not replace existing indemnity provisions made under the Clinical Negligence Scheme for Trusts (“CNST”) and it has been confirmed that the new Nightingale Hospitals will be covered by CNST rather than CNSC.  Similarly, NHS Resolution have confirmed that those doctors and nurses returning to practice from retirement, or those joining as students will be covered by the CNST or, where applicable the Clinical Negligence Scheme for General Practice (“CNSGP”).  The CNSC will not cover returning midwives to the profession, but the Royal College of Midwives have confirmed that they will extend all of the benefits of membership including Medical Malpractice Insurance to returning retired midwives.

For more information regarding this please click here.

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

What are the negatives associated with having MHFAs in the workplace and what is the best way to manage this without removing MHFAs from the company?

The only potential negatives are the potential for MHFAs to become overloaded, or for MHFAs to overstep the boundaries of their role. Both would be avoided if a suitable framework is in place around them, and if adequate ongoing support and training is provided.