Can I amend my divorce settlement due to Covid?
Maintenance Orders are capable of variation so if your income has reduced as a result of the pandemic, you may be entitled to reduce your payments. You should ensure that any reduction is reflected in a Court Order to ensure your ex-spouse cannot claim arrears from you.
It is not generally possible to vary capital and pension settlements included in Court Orders unless there has been a significant event, sometimes known as a “barder event”. The following four conditions must be satisfied:
- New events have occurred since the Order which invalidate the basis or fundamental assumption on which the Court Order was made and which were unforeseen and unforeseeable. This can include a change in the value of assets, employment status, inheritance and death.
- The new events occurred within a relatively short time of the Order being made.
- The Application to change the Order is made reasonably promptly.
- If the Application succeeded, this would not prejudice any third parties who have acquired assets in good faith e.g. if the family home has already been sold to a third party.
The applications relying on Covid as a significant event have had limited success. The circumstances in which the Barder principle may apply are few and far between. It is of note that the global financial crisis of 2007/2008 was not considered to be a Barder event.
Care should, therefore, be taken when deciding whether to pursue a change to the Divorce settlement and it is recommended that you speak to a specialist Family Law team like ours.
Related FAQs
On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.
Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.
As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.
These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.
This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?
For example:
- If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
- If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?