Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
It is worth pointing out that, despite all the guidance, survey results and other advice about managing Covid-19 H&S risk in the workplace, the law has not been changed. None of the guidance is codified by regulation/legislation, which means that you are managing this risk in the context of existing H&S law.
In very simple terms, HASWA74 requires employers to take “all reasonably practicable steps” to ensure the health and safety of its employees (and anyone else affected by your business).
“Reasonably practicable” means to balance risk reduction against the time, money and effort required. If measures are grossly disproportionate, you wouldn’t be expected to take them, but there is a strong presumption in favour of taking any steps which will protect workers.
As part of managing the health and safety of your people, you must control the risks in your workplaces. To do this, look for what might cause harm to people while they work and decide whether you are taking reasonable steps to prevent that harm. This related duty under MHSWR is to ensure you undertake a “suitable and sufficient assessment of risks.”
No, there is no obligation on employers to offer a flexible furlough arrangement to staff. Operationally, flexible furlough may not be appropriate for your business and equally, returning on a part-time basis may not be suitable for individuals already furloughed for various reasons. Concerns about returning to work part-time or at all should be considered on a case-by-case basis.
- Yes, and this includes furloughed employees under the Coronavirus Job Retention Scheme.
- Employers must continue to assess their new employees or newly eligible existing employees and enrol them where required, but can make use of the statutory postponement procedure which allows them to delay for up to three months the assessment of new employees for the purpose of enrolment (see further details here on the Pensions Regulator’s website). Declarations of compliance for new employers must still be completed in the normal way.
- Postponement cannot be used for re-enrolment. The Regulator recommends employers use the re-enrolment date tool on the Regulator’s website to choose a date up to three months after the third anniversary of enrolment to assess staff for re-enrolment. Further information about employers’ obligations about reenrolment from the Pensions Regulator can be found here. Re-declarations of compliance for new employers must still be completed in the normal way.
Yes. The Land Registry published a new service update on 14 May, here:
https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service
Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
To summarise some further points:
- Most information enquiries are experiencing minimal delays
- Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
- Cancellation dates for replying to requisitions are extended until further notice
- Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
- Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
- Requests for extensions to a notice or objection period will be granted if lawfully possible
- Land charges searches can be submitted electronically with PDF documents
The Town and Country Planning (Use Classes) (Amendment) (England Regulations) 2020 were laid before Parliament and come into force on 1 September 2020. They apply in England only.
The changes include the revocation of the following Use Classes;
- A1 – shops
- A2 – financial and professional services
- A3 – restaurants and cafes
- A4 – drinking establishments
- A5 – hot food takeaways
- B1 – business. Also revoked are the sub parts of B1;
- B1(a) – offices
- B1(b) – research and development of products and processes
- B1(c ) – industrial process
- D1 – non residential institutions
- D2 – assembly and leisure
The changes include the amendment of the following Use Class;
- B2 (industry)
The changes include the introduction of the following Use Classes;
- E – commercial, business and service
- F.1 – learning and non-residential institutions
- F.2 – Local community
There are no changes to the following Use Classes;
- C1 – hotels, boarding and guest houses
- C2 – residential institutions
- C3 – dwellinghouses
- C4 – small HMO
From 1 September 2020;
- Small retail shops (not more than 280 sq metres net sales area) selling essential goods including food and at least 1 kilometre from another shop will cease being an A1 use and will become a F.2 (local community) use;
- Other A1 shops will become an E (commercial, business and service) use;
- A2 uses will become an E (commercial, business and service) use;
- A3 uses will become an E (commercial, business and service) use;
- A4 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
- A5 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
- B1 uses (included B1(a), B1 (b) and B1 (c) will become an E (commercial, business and service) use;
- B2 uses will either be B2 uses or will be Class E uses.
- Clinics, health centres, creches, day nurseries and day centres (previously D1 uses) will become an E (commercial, business and service) use;
- Schools, non residential education and training centres, museums, public libraries, public halls, exhibition halls, places of worship, law courts (previously D1 uses) will become an F.1 ( learning and non-residential institutions) use;
- Cinemas, concert halls, live music performance venues, bingo halls and dance halls (previously D2 uses) and will be sui generis, ie not in any use class;
- Gyms, indoor sport, recreation or fitness not involving motorised vehicles or firearms principally to visiting members of the public (previously D2 uses) will become an E (commercial, business and service) use;
- Hall or meeting place for the principal use of the local community (previously D2 uses) will become an F.2 (local community) use;
- Indoor or outdoor swimming baths, skating rinks, outdoor sports or recreation grounds (not involving motorised vehicles or firearms) (previously D2 uses) will become an F.2 (local community) use.
Changes of use within a Use Class do not constitute development. That being the case, provided the Order is applicable, its operation not having been restricted by planning condition, Agreement or Article 4 (1) Direction for example, planning permission would not be required, development as defined not happening. If legally binding confirmation is required that planning permission is not required this can only be obtained by way of a successful application for a Certificate of Lawfulness. In the absence of such, there is some risk.
It remains the case that planning permission may be required for operational works to buildings. It also remains the case that other consents and permissions may be necessary for example licenses. Furthermore amendments to leases may be required if the property is rented.
The Regulations additionally include transitional arrangements because of permitted development rights for changes of use in the Town and Country Planning (General Permitted Development) (England) Order amongst others. To respond to this Regulations introduce a ‘material period’ which is defined as meaning the period beginning 1 September 2020 and ending 31 July 2021. It is expected during the material period the Orders giving permitted development rights for changes for use which do constitute development will be amended / updated to reflect the new use classes.
Click here to view the Regulations.
The above is based on our understanding of the new Regulations at the time of issue and in advance of planning practice guidance being issued.