Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

How do I make arrangements for end point assessments for apprentices?

Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.

Would it be appropriate to suspend someone who refuses to restrict their duties?

Suspension should always be a last resort and not a knee jerk reaction. We would not advise suspension unless a the above steps around the risk assessment have been undertaken. Depending on your local policies, suspension could then be an option on the basis that their health and safety and the health and safety of others are put at risk by their actions.

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

How does this protect businesses entering into an insolvency process?

The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.

Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance,  in the event that the customer enters an insolvency procedure.

This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.

Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.

Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.

I’m in the process of litigation. What happens during the coronavirus outbreak?

The best advice is that parties should proceed as they would have done before the crisis began.