Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
The application is made via the Companies House website, and only takes a few minutes to complete. Companies House have indicated that the extension is “automatic and immediate” and will be for three months.
Having said that the extension is “automatic”, their website also says that Companies that have already extended their filing deadline, or shortened their accounting reference period, may not be eligible for an extension.
If an extension is granted, it will not affect the due date for filing accounts in future years – so the deadline will revert to the usual date for the next accounting period.
As above, people must not leave their home unless they have a ‘reasonable excuse’ and travelling should be limited to their local area. Employees may leave their home and local area to travel for work if they cannot reasonably work from home. You should attempt to reduce the number of journeys they make.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
This guidance from the Chief Coroner applies to reports of death and coroner investigations in England and Wales. It is to assist coroners in continuing to exercise their judicial decisions independently, in accordance with the law, and during the extraordinarily pressured events being faced at present.
Initially, the relaxation applied to supermarkets and food suppliers. This was subsequently widened to apply to other businesses, permitting them to collaborate where necessary to respond to the crisis in the interests of consumers.