Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.
Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.
The key factors used to determine status are:
- Control:
- How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
- Personal service:
- Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
- Mutuality of obligation:
- Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?
During the Covid 19 crisis lawyers and the courts have had to adapt with hearings being heard remotely and with more electronic communication. It is clear that going forward, some of these changes will become more permanent.
The Lord Chancellor, Robert Buckland QC MP, has spoken last week regarding changes to the justice system following the COVID-19 pandemic and we know that there is a significant backlog of work that needs to be processed.
Firstly, 10 sites have been identified for ‘Nightingale courts’ which will allow for better social distancing. The authorities have suggested that it is a possibility that courts will need to stay open for a longer time or at weekends, to increase the number of cases that can be heard safely on any given day. This will enable more cases to be heard in a day and therefore a swifter outcome for your case. The standard of video technology will also continue to improve, with plans for new technology being rolled out across all courts form July onwards. The enhanced use of technology may result in matters being heard more efficiently, decreasing the time spent during each hearing.
HMCTS is working to expand access to audio and video technology to support more and new types of hearings. There has been an increase in the use of new and varying equipment over the lock-down period. With the appropriate systems in place, many more hearings could take place on platforms such as the Cloud Video Platform (CVP). Throughout July, the CVP will be more readily available to Country courts. There will be further hardware rolled out to improve the quality of video hearings, and there will be more efficient methods used to organise video lists.
The increased use and training of CVP means that witnesses and advocates may not need to attend court and could attend the hearing remotely. This will give you increased flexibility, enabling you to attend from your office or home. The CVP is efficient and simple to use, with no complex functions; making it user-friendly. This should make litigation more time and cost effective (albeit that there will be the cultural challenge of having less contact with your legal team or the court experience).
It is envisaged that employees of organisations falling into the first two categories set out above and won’t be eligible for the job retention scheme in relation to the majority of their employees. It is envisaged that NHS Trusts for example are going to require their staff to be working at full capacity where possible. However, the guidance doesn’t definitely exclude public sector organisations from furloughing employees and notably the government expects such organisations to use public money to continue to pay staff and not furlough them, rather than say requires. In reality, it is difficult to see how such an organisation will be able to rely on the scheme, but the guidance doesn’t completely rule it out.
Employees with visas should be treated consistently with the wider workforce. When their furlough leave ends, they should return to work and their pay should be reinstated. If you agree a pay cut or reduction in working hours, you need to ensure that sponsored workers are still earning above the minimum salary for their role and working in excess of the minimum number of hours (see above).
The flexible furlough scheme is now in place and can be used for employees who have previously been furloughed for a consecutive period of at least three weeks. The flexible furlough scheme remains in place until 31 October 2020.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.