Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Overall it is our experience that the Courts are quickly adapting in the context of the Coronavirus epidemic and making pragmatic decisions. The Judges seem live to the difficulties currently been faced by practitioners dealing with litigation and they are applying the new guidance.
The Courts are also mindful of pressures on NHS frontline staff and are taking steps not to put additional pressures on them at this time, including in our experience vacating an imminent Trial.
Where an apprentice is made redundant the training provider should support the apprentice in seeking alternative employment within a 12 week period. ESFA will support this process. Where an apprentice is placed on unpaid leave or the nature of their employment no longer supports their apprenticeship, it should be considered whether a break in learning would be appropriate.
An employer who wishes to make an apprentice redundant should seek advice on the process to be followed for this.
Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.
In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.
The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.
The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.
On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.
A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.
The Act has introduced the following restrictions:
- A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
- A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
- When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
- All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
The reaction from NCVO is that this is an important first step. However, it will not stop well run charities from closing and others will look very different in a few months’ time.