Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
A number of our clients and networks raised issues in the early stages of the Scheme around the requirement for personal guarantees to access finance under the Scheme. The Scheme has now been updated so that:
- For facilities under £250,000, personal guarantees cannot be taken to support lending under the Scheme.
- For facilities above £250,000, personal guarantees may still be required by a lender but the amount which can be recovered under these guarantees is capped at a maximum of 20% of the outstanding balance of the CBILS facility after taking into account any other recoveries from business assets.
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
Where it is envisaged that 20 or more employees will be dismissed at a relevant establishment within a 90 day period or less, then collective consultation is required (in addition to individual consultation) and the company must inform BEIS (using form HR1).
If there are less than 20 dismissals then you are only required to carry out individual consultation.
Yes. The Land Registry published a new service update on 14 May, here:
https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service
Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
To summarise some further points:
- Most information enquiries are experiencing minimal delays
- Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
- Cancellation dates for replying to requisitions are extended until further notice
- Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
- Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
- Requests for extensions to a notice or objection period will be granted if lawfully possible
- Land charges searches can be submitted electronically with PDF documents
There is not currently a requirement for MHFAs to be DBS checked.