Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

Other considerations – the mental health and wellbeing of BAME staff and others

Undeniably and understandably BAME staff, as well as those staff who are identified as being at a higher risk, are going to have high levels of stress and anxiety. For some, this may become of such severity that those staff should be considered to be disabled under the Equality Act 2010. The question as to whether someone is disabled is one that should be answered in conjunction with appropriate medical advice. But the question about how to support any staff suffering with stress and anxiety should not be left until that stage. Proactive steps need to be taken and expert advice obtained on what support measures should be put in place. We know that many NHS organisations are already giving the mental wellbeing of their staff the highest priority.

From our perspective, we would ask managers to be mindful that stress and anxiety is likely to feature in how an individual reacts to questions about the level of risk to their health and the impact on their duties. The conversations with some staff may not be easy to have and may be met with challenge.

For those staff who’s stress and anxiety is such that it would qualify as a disability, reasonable  adjustments will need to be considered to the processes that you are applying.

An additional point to consider – it might be worth writing to all staff, asking them to come forward if they have any health conditions that they think you ought to be aware of, assuring them that such information is being given in the strictest confidence. You want to make sure that you are taking the appropriate measures to ensure their health and safety.

VIDEO: Redundancy exercises in the new normal – what should we do differently?

Following our webinars on all aspects of furlough and alternatives to redundancy, it is an unfortunate fact that a number of organisations are likely, sooner or later, to be forced to make some employees redundant.

Our employment experts Jamie Gamble and Roisin Patton take you through the key aspects of conducting cost reduction redundancies, but with a focus on aspects that make this exercise different this time. For instance:

  • How are you going to conduct sensitive meetings remotely?
  • How are you going to ensure that dismissing any furloughed staff will be fair? You may have furloughed at speed, but redundancy selection criteria cannot be defined by such factors.
  • Will you use this time to review your selection criteria if you already have some in place?
  • How will you deal with individuals who are shielding, have child care issues or are pregnant?
  • How do you ensure this is all done sensitively and fairly for those roles that are being made redundant, but also for those who continue to work for you but are still isolated on furlough or working from home?
  • And what are the risks for making redundancies in this “new normal”?

Although you may be perfectly familiar with redundancy exercises these are far from normal times and it is therefore worth pausing to think about the impact that Covid-19 might have and what else you need to think about or plan for.

The webinar was recorded on Thursday 2nd July.

 

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.