Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.
Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.
The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.
Despite remote hearings being the default position at present, formal permission will still be required by the court and a template order was circulated with the guidance. This template sets out the relevant directions and recitals to include in your order. An application to the COP for a remote hearing will not be required.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
Potentially no.
If an employer is not put on notice that the circumstances of a worker or agency worker are such that they ought to be self-isolating, by either the worker or agency worker themselves or another member of staff, then there ought to be a reasonable excuse, and potentially, no fixed penalty notice will be issued.