Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What are the responsibilities of employers under the coronavirus Test and Trace scheme?

The Government has produced workplace guidance for employers, setting out 2 key messages for employers:

  • Continue to make workplaces as safe as possible; and
  • Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate

Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

If an employee works with vulnerable people who are at high risk of catching coronavirus, can the employer require them to limit their activities outside of work?

It is unlikely that an employer can place such a requirement on staff without infringing the employee’s privacy. If the employee is acting in accordance with the rules, limiting their activity would likely be considered unreasonable.

How does COVID-19 affect Right to Work checks?

All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.

How is an establishment defined?

The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:

  • A distinct entity
  • With a certain degree of permanence and stability
  • Which is assigned to perform one or more tasks
  • Which has a workforce, technical means and a certain organisational structure to allow it to do so

However, there is no need for it to have the following:

  • Legal, economic, financial, administrative or technological autonomy
  • A management which can independently effect collective redundancies
  • Geographical separation from the other units and facilities of the undertaking