Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Employees who are union or non-union representatives may undertake duties and activities for the purpose of individual or collective representation of employees or other workers. However in doing this, they must not provide services to or generate revenue for, or on behalf of your organisation or a linked or associated organisation.
Employees who are pension scheme trustees or trustee directors of a corporate trustee may also undertake trustee duties in relation to the pension scheme. However, a professional, independent pension scheme trustee who has been furloughed by the independent trustee company cannot undertake trustee work that would provide services to or generate revenue for, or on behalf of, the independent trustee company or any organisation linked or associated with that independent trustee company during hours when they are recorded as being on furlough.
The guidance is helpful and is likely to be useful to businesses as they seek to respond to the crisis and to restart their business activities as lockdown is eased. However, there remain outstanding questions. For example, can collaboration to prevent widespread insolvencies be viewed as in the interest of consumers? Businesses need to remain aware of the extremely high stakes involved in relation to competition law. Businesses contemplating collaboration with competitors should take legal advice before doing so.
No. Before continuing any negotiations, you need to strongly consider whether now is the best time to settle. There is a myriad of uncertainty due to the pandemic, with unemployment rates increasing, volatility in the stock markets and difficulties regarding placing valuations on assets. This could all lead to the financial settlement being unfair to you and cause you financial difficulties in the future.
Any financial settlements reached following marital separation should be embodied in to a Court Order, to prevent future claims from your ex-spouse. As a general principle, although maintenance orders are always variable, financial orders in respect of capital (e.g. house, cash, investments, pensions) are final and it is very difficult to set aside a Court Order. The question will be whether or not the pandemic is judged as a Barder event, which broadly means something viewed as unforeseen. It would be challenging for you to argue that the effects of COVID-19 are unforeseen given the widespread expectation of an economic crisis. The Court previously found against a husband who wanted to revisit an Order that he said was unaffordable following the 2008 financial crisis, with one Judge commenting that a 90% drop in the Husband’s share price was a “natural process of price fluctuation”.
Even if you informally agree a settlement with your ex-spouse, and you do not have this reflected in a Court Order, your ex-spouse may still rely on this agreement within future Court proceedings and argue that you should be held to it.
It is, therefore, very dangerous to be reaching any financial settlements at this time with your ex-spouse without careful consideration and legal advice. Further, even if an agreement is reached, market volatility can mean longer implementation times, especially when a settlement relies on the sale of property.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.
Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.