Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
The guidance has confirmed that all remaining employment rights and terms continue while an employee is furloughed. Holiday will continue to accrue during furlough however you may reach agreement with employees on reducing entitlement provided that it does not fall below the statutory minimum of 5.6 weeks per year.
The ICO is providing new guidance to organisations regarding data protection and coronavirus, which can be accessed here: https://ico.org.uk/for-organisations/data-protection-and-coronavirus/
Information about the Covid-19 health status of individuals is special category data under the GDPR. This means it is high risk which has implications for how you use it, store it and keep it secure.
You will already hold health data about your employees as this is necessary to provide a safe, accessible place to work and to make reasonable adjustments to the workplace. You now need to make sure that the information you gather about your employees, visitors to your sites, customers and suppliers about Covid-19 is processed in accordance with data protection laws.
Potentially. The first question is why the person is not able to return, as their individual circumstances will be very relevant in terms of whether they can be safely dismissed.
Employers should ask themselves 2 questions in this situation:
- Have I done everything I am required to do in order to make the workplace safe for the individual to return; and
- Is what the employee saying reasonable?
If the answer to question 1. is no then a dismissal is unlikely to be fair. However, even if the answer to question 1. is yes, then there is still question 2. to address. If the employee has reasonable grounds as to why they are unable to return to work, e.g. due to health issues, childcare responsibilities etc then the dismissal is unlikely to be fair. It is only if you can answer yes to question 1. and no to question 2. that you can have some confidence in the potential safety of the dismissal.
Dismissals based on objections to returning to work on health and safety grounds will very often be risky and are highly fact specific, therefore please contact one of the employment team for further advice prior to dismissal.
Court hearings have been conducted remotely, with the judgment in Kerry v SSCLG being given via telephone. The Senior President of Tribunals issued emergency Practice Directions which will apply to Property and Lands Chambers’ respectively. This has made provision for remote hearings. Inspections of properties have been suspended with immediate effect, with photographs, videos or external visits permitted where appropriate. Where inspections are essential, the case should be stayed.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs