Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

How may proceedings change after Covid-19?

During the COVID-19 global pandemic, trials and hearings have been mostly conducted over Skype for Business and various other online platforms. Looking forward to the future, what we have experienced during the lock-down may continue and we believe will make litigation a more streamlined, user friendly experience for litigants.

One example of a regime which has been introduced is hybrid trials for lower value claims. Hybrid trials allow for parties and their witnesses to be linked into the court room by video link, whilst the judge and advocates are present in court. This makes it easier and frees up more time for witnesses, which would otherwise be spent in travel and waiting time, especially for those with other commitments.

With hybrid trials, clients still get a full legal experience and the judge will still apply normal legal principles during the trial. The procedure for the case is the same, both leading up to the trial or hearing and during the case itself; except without the need to physically attend court. It may also mean that there will be less of a backlog arising from the current crisis with cases continuing to be heard, allowing for matters to be listed earlier and a quicker outcome for the parties involved.

The shift to the use of online platforms may prove more practical for all those involved in legal matters. Interim hearings can be heard remotely resulting in a time and cost saving for litigants. Even for the final hearing only the legal representatives need to attend court – again resulting in time and cost savings for all concerned.

I have trespassers occupying my land. Can I evict them?

On 18 April 2020, it was announced that an exception to the current stay in possession proceedings and ban on all evictions has been made to allow possession orders to be made against trespassers.

This means land owners can take action to remove unauthorised persons occupying their land. Trespassers include: squatters; travellers; failed successors of secure tenancies; and licensees whose licences have been terminated.

Further, the automatic stay to possession proceedings currently imposed no longer applies to applications for interim possession orders meaning any persons found to be “squatting” on land without permission may again be subject to an order requiring them to leave your premises within 24 hours of service of that order.

What happens if I need to sign a new commercial lease in the future?

The outbreak is certainly going to have an impact on new lease negotiations.

Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.

It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.

In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.

Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.

What are the additional costs for the end user if the contractor is deemed employed?

The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.

Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.

What records do I need to keep for Flexible Furlough?

You will need to keep a copy of the written agreement for a period of 5 years. If the hours of work change from that which you initially agree, you are likely to need something new in writing to cover each separate arrangement.

You should also keep records of how many hours your employees work and how many hours they are furloughed (i.e. not working). You must keep these records for 6 years, together with a record of the amount claimed, your claim reference number and your calculations.