Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Would you suggest using a different name for a MHFA, maybe a MH champion, to encompass the wider pro-active role?

This may be a good idea – whatever name they are given, it is essential that MHFAs are empowered to take a proactive approach to organisational mental health and that they have the bandwidth to be able to discharge their responsibilities.  The name should reflect the culture of the organisation, the key aspect is awareness and accessibility – identifying a name for your company that supports this is key.

Can I collect health data in relation to Covid-19?

Yes. With respect to employees you have an obligation to protect their health so you can gather information to do that. You might gather information from your employees on who has the virus, who has had it and recovered and also who has tested negative. You might also want to know if individuals have been in contact with someone who has it or if they are in a vulnerable group. It is reasonable to want to know where individuals have travelled. In the future it may also be reasonable to know if they are planning to travel to a virus hot spot, as the impact of the virus around the world is likely to continue for some time even after the outbreak has been contained in the UK.

It is reasonable to gather some information about visitors to your site, be they customers or suppliers, as this information will also help protect your staff. However, you should keep what you gather to a minimum. For visitors, it’s unlikely that you need to know anything more than they have Covid-19, are displaying symptoms or have recently been in contact with someone who has the virus.

Court proceedings have been issued. What happens to the court timetable?

The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.

What options do I have if I have staff with childcare responsibilities but their job cannot be done at home?

If it is not possible to find work for the employee to do at home, you do have the option of putting the employee on furlough.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.