Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Funding audits are being paused and no new audits will be commenced during the lockdown period.
Employees are generally permitted to take holidays during furlough. However, Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.
Employees continue to accrue leave during furlough (whether they are on full furlough or flexible furlough) and can take leave during periods of Flexible Furlough (so long as you top the grant up to full pay for any days taken as holiday).
Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.
The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.
If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.