Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
It is a theoretical possibility that “anti-vax” beliefs could be a philosophical belief under the Equality Act 2010 and therefore anti-vaxers have the right not to be discriminated against for their beliefs. Much will depend on why the individual is against the vaccine. Conspiracy theorists (the vaccine is being used as an opportunity to monitor you or it’s all because of 5G) are highly unlikely to be treated as having a philosophical belief!
Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.
Sections of the video and their timings are as follows:
(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)
(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II
(05.36) – bounce back loans have been a distraction
(06.27) – muted impact of fintech CBILS lenders
(07.52) – discussion about invoice discounting
(11.59) – looming insolvency environment
(12:52) – emerging themes
That will depend on the terms of your facility and the stance taken by your bank.
Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).
The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.
Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
The outbreak is certainly going to have an impact on new lease negotiations.
Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.
It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.
In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.
Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.