Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

I work in construction. Can I still travel to work?

The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.

The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures.  If it is not possible to work in accordance with the above they should not work.

How can RPs carry out Person Centred FRAs/PEEPs on tenants within directly managed supported living units where the RP is not providing support and any floating support provider doesn't see it as part of their responsibility?

There is no simple answer.

The NFCC guidance states:

“The person-centred fire risk assessment is intended only as a simple means for non-specialists who have suitable understanding of relevant fire risks to determine whether additional fire precautions might be needed. The person who carries out the person-centred fire risk assessment will depend on the circumstances of the housing and support provision. It can be carried out by those who regularly engage with the resident, with input from specialists where necessary. Assessments will normally be undertaken with residents themselves.

In sheltered housing with scheme managers, the scheme managers normally engage with residents on a routine basis, enabling residents who need a person-centred fire risk assessment to be identified. Many vulnerable residents will be in receipt of care, so enabling the care provider to identify residents in need of a person-centred fire risk assessment. Providers of regulated care are required to take into account risks to people from their wider environment, to take steps to help people ensure that they are dealt with by appropriate agencies, or to raise safeguarding alerts when this is appropriate. Where a ‘stay put’ strategy is adopted, there will be a need to identify residents who need assistance from the fire and rescue service to evacuate the building.

In supported housing, the number of residents in each property is usually quite small. This, and the nature of the care service normally provided, enables person-centred fire risk assessments to be carried out asa matter of course, when a resident first moves into the property.

Where additional fire precautions cannot be provided in the short term, the risk should be reduced as far as reasonably practicable and an adult at risk referral should be made to Adult Social Care.”

Ideally then the RP will need to engage with any care providers in order to conduct the PCRA and identify risk mitigation measures. If they are reluctant to do so, the RP should engage with the individual in any event in undertaking the assessment.

How the furlough scheme changed from 1 July – what is flexible furlough?

From 1 July 2020 the furlough scheme has been operating more flexibly.

The key changes from 1 July 2020 were:

  • All furloughed employees are subject to the new flexible furlough rules and the new basis for calculating claims
  • Furloughed employees can be brought back to work on a part-time basis for any amount of time and can work any work pattern
  • Employers can claim for the hours not worked compared the hours the person would normally have worked in that period
  • There must be a new written furlough agreement in place to record the agreement with the furloughed employee to return to work part-time
  • The new agreement (including a collective agreement) must be made before any period of flexible furlough begins but it may be varied at a later stage if necessary. The agreement must be incorporated into the employee’s contract of employment, either expressly or impliedly
  • Employers must keep a record of this agreement until at least 30 June 2025, and they must also keep a record of the hours the furlough employee worked and the hours that they were furloughed
  • Employees can be furloughed from 1 July 2020 for any amount of time and more than once
  • However, if you re-furloughed an employee after 10 June but before 1 July 2020, they had to be furloughed for an initial period of three consecutive weeks
  • Claims for payments under the scheme must not cross calendar months so if you are claiming for the initial three week period of a re-furloughed employee who was furloughed on 12 June for example, you must submit separate claims for the dates in June and July
  • Although flexible furlough agreements can last any length of time, you should only submit a claim to HMRC once a week.
What security will be required for CBILS?

At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.

Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS.  As a result  it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.

Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.