Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
My visa is about to expire, can I apply to extend it?

Yes, you should submit a new visa application before your current visa expires.

The visa application is a two stage process:

  • First you submit the online application and pay the fee
  • Second you attend a visa application centre to enrol your biometrics and verify your passport.

Submitting a valid online application before your current visa expires secures your right to continue living and working in the UK, even after your current visa has expired.

Visa application centres across the world have been closed due to covid19 but are now mostly re-open to enable you to book an appointment to complete your application, albeit some are experiencing a backlog of applications.

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

I work in construction. Can I still travel to work?

The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.

The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures.  If it is not possible to work in accordance with the above they should not work.

Is there anything I can do to try and settle my claim?

There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.

Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.

A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.

ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”