Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
MHFAs are not qualified mental health medical professionals and they should not be diagnosing or giving medical advice, however, their training will equip them to provide initial support to those experiencing symptoms of mental ill health, and to signpost to further professional help when needed. The MHFA training makes the boundaries of the MHFA role very clear and there should be clearly defined role specifications, procedures and support pathways in place to ensure that individuals are referred on appropriately. There should be peer support in place for MHFAs and a system in place to ensure no individual or individuals are overloaded.
If you don’t want to make redundancies, or if you can’t reduce employee resource, either in a particular department or across the workforce as a whole, then you need to think about alternatives to redundancy.
Equally, you may want to flex the resource you have available to you – without making drastic changes. For example you may want to consider:
- unpaid leave and sabbaticals
- retraining and redeploying
- forcing annual leave
- flexible working
- capability issues
- lay off
- short time working
- reductions in salary
- reductions in working hours
- changing to shift working
The FCA’s test case in the Supreme Court ruled overwhelmingly in favour of policyholders. However, business interruption cover generally has the prerequisite of physical damage or loss to the property (or in some circumstances, the presence of a notifiable disease at the property or within a certain radius of it), to recover losses caused by the interruption to your business. The onus is on insurers to re-assess those claims which are impacted by the Supreme Court’s judgment and to make contact with the policyholders regarding next steps. If you have not already made a claim, in the first instance the terms of any policy should be checked carefully to see whether business interruption cover is provided.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
No one factor will determine status and the outcomes will differ depending on the nature of the work being carried out and the business of the end user client.
When you have carried out an assessment based on the relevant factors you can either get in touch with us to discuss further, check your answers against HMRC’s CEST tool or do both before making a final determination.