Are Public Bodies able to continue to pay contractors (and their supply chains) at risk as a result of Covid-19?

Yes: The Cabinet Office has published a number of Procurement Policy Notes to provide instructions to Public Bodies to enable payments to continue to be made to at risk suppliers (and their supply chains) who have been affected by Covid-19. Copies of this guidance can be obtained from the Government website at: https://www.gov.uk/government/publications/procurement-policy-note-0220-supplier-relief-due-to-covid-19

Related FAQs

Are there any exceptions to the obligation to return deposits?

The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.

This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.

The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.

Should we issue petitions?

Our advice to you here is simple. It will depend on the circumstances surrounding your debt but for the most part, unless it is crystal clear that there has been a debt outstanding long before Covid-19 and there was an inability to pay prior to the Covid situation we would recommend that you hold off issuing any further petitions until after the 31st December. Unless the criteria set out above is met, a judge is likely to exercise their discretion leniently and could dismiss the petition. This could also lead to cost consequences which would adversely affect you.

We are happy to discuss individual cases to assist creditors at this difficult time, however, generally any cases proceeding to petition would be the exception as opposed to the rule. Even if presenting a winding up petition is not available for now, there may still be other forms of legal proceedings that you can use to collect money owed to you, like county court proceedings.

What records do I need to keep for Flexible Furlough?

You will need to keep a copy of the written agreement for a period of 5 years. If the hours of work change from that which you initially agree, you are likely to need something new in writing to cover each separate arrangement.

You should also keep records of how many hours your employees work and how many hours they are furloughed (i.e. not working). You must keep these records for 6 years, together with a record of the amount claimed, your claim reference number and your calculations.

What are the new Procurement Policy Notes (PPN)?

The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.

PPN 01/20: Responding to COVID-19

The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.

This PPN provides guidance for the following circumstances:

  • Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
  • Direct award due to an absence of competition or protection of exclusive rights
  • Call off from an existing framework agreement or dynamic purchasing system
  • Call for competition using a standard procedure with accelerated timescales
  • Extending or modifying a contract during its term

PPN 02/20: Supplier relief due to COVID-19

PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.

This PPN provides guidance for the following circumstances:

  • Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
  • Put in place appropriate payment measure to support supplier cash flow
  • Where contract payments are based on ‘payment by results’ make payments based on previous invoices
  • Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
  • Ensure invoices submitted by suppliers are paid immediately on receipt

PPN 03/20: Use of Procurement Cards

The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.

This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:

  • Increase a single transaction limit to £20,000 for key card holders
  • Raise monthly limits on spending with procurement cards to £100,000 for key card holders
  • Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs

Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.

The PPN also advises that by 30 April 2020, in scope organisations should:

  • Ensure that a number of appropriate staff have the authority to use these cards
  • Open all relevant categories of spend to enable these cards to be used more widely
Will site visits, hearings and inquiries still take place?

Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.

The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .

The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.

Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.

The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.