Are permitted development rights now in existence for the creation of emergency medical facilities?
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Related FAQs
As part of the Coronavirus Bill there is some good news for tenants in so far as it included the following:
- All commercial tenants in England, Wales and Northern Ireland missing rent payments are to benefit from a government ban on forfeiture of their lease.
- Landlords then will be prevented from terminating leases and “evicting” commercial tenants.
- The above provisions rules will apply not only to principal rent, but to “any sum a tenant is required to pay”, leaving the burden of supplying services and insuring the premises on landlords. The bill will last until 30 June 2020, with an option for the government to extend this deadline.
Whist this is helpful to any Tenant planning not to pay rent or other payments due under their lease insofar as they will not suffer forfeiture and be evicted, it should be noted that the contractual obligation to continue paying rent and all other costs due under the lease remains and Landlords will still be able to take action to recover any payments due under the lease that are in arrears.
If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.
If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Residents will be obliged to:
- Not act in a way that creates a significant risk of a building safety risk materialising
- Not interfere with building safety equipment in the common parts
- Comply with an Accountable Person’s request for information in relation to the assessment and management of building safety risks.
The Accountable Person then has powers in relation to these duties, including:
- Issuing a contravention notice, requiring a resident to pay for replacement or repair of safety equipment which they have interfered with
- Applying for court orders in certain situations
- Requesting access at a reasonable time (in writing with at least 48 hours’ notice) to a resident’s property for the purposes of assessing or managing building safety risks, or checking compliance with the resident’s duties as above.
Secondary legislation is still awaited to bring these provisions into force, so the timing is unknown, but it will likely be within the next 12 months in line with the anticipated timetable for the remainder of the Act.
Contractors working for public sector organisations who are deemed employees for IR35 purposes may be eligible to be furloughed provided they are paid via PAYE. In this scenario the agreement to furlough would be made between the contractor’s personal service company (PSC) and the fee payer (usually the agency). The parties would agree that the contractor will carry out no work for the public sector organisation while furloughed and the fee payer would apply for the grant.
At the moment the guidance states that in order to be eligible a claim for furlough must have to have been submitted by 31 July 2020 for a period of 3 weeks between 1 March and 30 June 2020.