Are permitted development rights now in existence for the creation of emergency medical facilities?
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Related FAQs
HM Treasury have no current plans to pause the collection of apprenticeship levy payments from employers, therefore levy-paying employers must continue to make payments. There is also no plan to extend the 24 month period allowed to spend levy funds.
If you don’t want to make redundancies, or if you can’t reduce employee resource, either in a particular department or across the workforce as a whole, then you need to think about alternatives to redundancy.
Equally, you may want to flex the resource you have available to you – without making drastic changes. For example you may want to consider:
- unpaid leave and sabbaticals
- retraining and redeploying
- forcing annual leave
- flexible working
- capability issues
- lay off
- short time working
- reductions in salary
- reductions in working hours
- changing to shift working
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
The key factors for determining status for employment and tax purposes are generally the same. However there are some cases that highlight the different approaches taken by employment tribunals and HMRC when determining status. The important thing to consider for IR35 purposes is that being deemed employed for tax purposes does not mean a contractor is ’employed’. PSC’s can still be used in moving forward but there are likely to be discussions on the commercial aspects of the contractor arrangement. Employment status for tax purposes is likely to come at a cost for both parties.