Skip to content

Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made

Related FAQs

What should I do about non-urgent repairs?

As discussed above, Covid-19 will inevitably deplete the workforce of housing providers in the foreseeable future. It would be prudent to consider making short-term policy changes to deal with this situation and manage the expectations of tenants going forward. A key policy change to consider is the extension of the standard lead-time for completing all non-urgent repairs and inform tenants of this change.

Such a change will also reduce pressure on landlords and front-facing staff.

As above, employers must protect the interests of their staff, particularly regarding health and safety. Extra care should be exercised when assessing the level of emergency of a repair on a case by case basis. All efforts should be made to reduce the number of attendances at properties by repair staff, whilst keeping all tenants safe.

As ever, communication is key – the pandemic cannot be used as a blanket excuse for abstaining from all duties and obligations. Housing providers must take a pragmatic approach in safeguarding customers whilst considering the interests of is workers. Maintaining lines of communication with all parties remains paramount.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

I’m a landlord. How do I comply with Regulation 36 of the Gas Safety Regulations 1998 during the coronavirus outbreak?

Under their obligations arising from Regulation 36 of the Gas Safety (Installation and Use) Regulations 1998, landlords must service domestic gas appliances on an annual basis and provide tenants with a record of the service within 28 days of that service. Failure to comply can result in prosecution by the Health and Safety Executive (HSE) or downgrading by the Regulator.

We know how important this is. But how can you comply with your obligations during the Covid-19 epidemic?

The latest restrictions on leaving the home, currently allow registered gas engineers to undertake essential work, whilst taking the appropriate precautions advised to avoid spreading or contracting the virus in a new setting.

Reductions in salary

An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.

Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.