Skip to content

Alternatives to redundancy toolkit

We have developed a Toolkit to help with these issues. The Toolkit contains:

  • LO1 How to Guide: Lay off and short time working
  • LO2 Letter directing employee to take annual leave
  • LO3 Letter confirming lay off (contractual right)
  • LO4 Letter confirming short time working (contractual right)
  • LO5 Letter proposing lay off (no contractual right)
  • LO6 Letter proposing short time working (no contractual right)
  • LO7 Counter notice disputing entitlement to claim redundancy payment
  • LO8 Script for announcing lay off or short time working (contractual right)
  • LO9 Script for announcing lay off or short time working (no contractual right)
  • LO10 Letter proposing reduction in working hours and pay

The cost of this Toolkit is £500 plus vat. If you would like to find out more about the Toolkit, please speak to your usual Ward Hadaway employment contact, or get in touch one of the contacts at the bottom of this page.

Related FAQs

What is the amendment to The Working Time legislation called?

The government introduced The Working Time (Coronavirus) (Amendment) Regulations 2020 to amend the Working Time Regulations 1998 to allow for the change.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
The proposed start date on the Certificate of Sponsorship is about to pass, what do I do?

Sponsors should update the proposed start date by adding a sponsor note to the CoS via the Sponsor Management System.
Does a sponsor need to report a change in workplace if a Tier 2 visa holder is working from home as a result of Covid-19?

How is the Court of Protection dealing with matters during the Coronavirus pandemic?

The current situation with the coronavirus pandemic has presented obvious challenges to the effective and fair operation of the Court of Protection (COP). Remote access to the COP has therefore become a necessity to ensure that hearings continue to provide proper access to justice. All parties involved in such cases have a responsibility in achieving this primary aim.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.