Alternatives to redundancy toolkit
We have developed a Toolkit to help with these issues. The Toolkit contains:
- LO1 How to Guide: Lay off and short time working
- LO2 Letter directing employee to take annual leave
- LO3 Letter confirming lay off (contractual right)
- LO4 Letter confirming short time working (contractual right)
- LO5 Letter proposing lay off (no contractual right)
- LO6 Letter proposing short time working (no contractual right)
- LO7 Counter notice disputing entitlement to claim redundancy payment
- LO8 Script for announcing lay off or short time working (contractual right)
- LO9 Script for announcing lay off or short time working (no contractual right)
- LO10 Letter proposing reduction in working hours and pay
The cost of this Toolkit is £500 plus vat. If you would like to find out more about the Toolkit, please speak to your usual Ward Hadaway employment contact, or get in touch one of the contacts at the bottom of this page.
Related FAQs
Whilst it is acknowledged that doctors may be working in unfamiliar circumstances or surroundings, or in clinical areas outside their usual practice. Doctors should consider the best course of action to take in these circumstances by utilising the following:
- What is within their knowledge and skills
- What support other members of the healthcare team could offer
- What will be best for the individual patient given available options
- The protection and needs of all patients they have a responsibility towards
- Minimising the risk of transmission and protecting their health.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
We have developed a toolkit to assist with compliance. The Toolkit contains a specimen contract; detailed guidance; step by step guides and flowcharts; details of the factors to take into account for the status determination test; procedures for challenging the determination; and standard letters for the process. Click here to fill in a form and register your interest in the Toolkit, which contains:
- Detailed guidance in the form of Key Facts
- Employment status checklist
- Employment status assessment flowchart
- Status questionnaire and guidance
- Letter confirming self-employed status (agency)
- Letter confirming employed status (agency)
- Letter confirming self-employed status (direct with PSC)
- Letter confirming employed status (direct with PSC)
- Status disagreement process guidance
- Status disagreement process flowchart
- Letter confirming outcome of status disagreement process
- Consultancy agreement