Will the golden thread requirements in relation to maintaining a central record of building info be retrospective?
The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.
Related FAQs
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Commercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.
This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.
HM Treasury have no current plans to pause the collection of apprenticeship levy payments from employers, therefore levy-paying employers must continue to make payments. There is also no plan to extend the 24 month period allowed to spend levy funds.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.