Skip to content

Will site visits, hearings and inquiries still take place?

Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.

The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .

The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.

Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.

The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.

Related FAQs

What is the reaction to the funding?

The reaction from NCVO is that this is an important first step.  However, it will not stop well run charities from closing and others will look very different in a few months’ time.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

What guidance has the CMA issued about how it expects businesses to behave in response to the global pandemic?

On 30th April 2020, the CMA issued a guidance note setting out its views about how the law operates in relation to refunds.

Where a contract is not performed as agreed, the CMA considers that in most cases, consumer protection law will generally allow consumers to obtain a refund.

This includes the following situations:

  • Where a business has cancelled a contract without providing any of the promised goods or services
  • Where no service is provided by a business, for example because this is prevented by Government public health measures
  • A consumer cancels, or is prevented from receiving any services, because Government public health measures mean they are not allowed to use the services.

In the CMA’s view, this will usually apply even where the consumer has paid what the business says is a non-refundable deposit or advance payment.

This positon reflects the CMA’s previous guidance which they had issued in relation to the requirement of fairness in consumer contracts under the Consumer Rights Act 2015, which was that a clause in a contract that gives a blanket entitlement to a trader to cancel a contract and retain deposits paid is likely to be unfair, and therefore unenforceable – it would be unfair to a consumer to lose their deposit if the contract is terminated without any fault on their part, and if they had received no benefit for the payments made.

The CMA’s latest guidance therefore confirms their view that the Covid-19 outbreak does not change the basic rights of the consumer, and that they should not have to pay for goods or services that they do not receive.

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
What should payroll look out for if the Government's Coronavirus Job Retention Scheme is used?
  • It is important to have a clear paper trail for any agreed reduction in salary, and hence any reduction in the amount of contributions. However, the contribution rates (as opposed to the amounts) should be the same as normal, and hence all processes and software should function as per normal and, amongst other things, remain compliant with auto-enrolment employer duties.
  • However, if the period of affected contributions does not overlap precisely with the period of reduced salary, for example because of different cut-off dates, there may well be instances of non-compliance with auto-enrolment employer duties at the beginning as well as at the end of the period covered by the Coronavirus Job Retention Scheme.
  • Accordingly, where an employer takes advantage of the Coronavirus Job Retention Scheme, good communication with the persons responsible for pensions administration and detailed record-keeping are essential to prevent non-compliances in the short-term and confusion in the long term.