Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Related FAQs
Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.
Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19
In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
An obvious cost cutting measure is to reduce salaries, either temporarily or permanently. If you are to seek a reduction in salaries, this should be done fairly – either across the board or by selecting teams/individuals based on objective business reasons.
Note that this cannot be imposed without significant risk. Without agreement, this would need fair selection and consultation.