Who is responsible for planning in the event of an excess of deaths?
In the unfortunate event that there will be a significant number of deaths, planning will fall to the local resilience forum; which includes all relevant local organisations and statutory bodies, who will have prior experience in working in excessive death scenarios.
It is for the coroners to ensure that they are familiar with the local resilience forum plans and discussions required. This will include issues regarding storage capacity and post-mortem examination capacity.
Related FAQs
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Contractors working for public sector organisations who are deemed employees for IR35 purposes may be eligible to be furloughed provided they are paid via PAYE. In this scenario the agreement to furlough would be made between the contractor’s personal service company (PSC) and the fee payer (usually the agency). The parties would agree that the contractor will carry out no work for the public sector organisation while furloughed and the fee payer would apply for the grant.
At the moment the guidance states that in order to be eligible a claim for furlough must have to have been submitted by 31 July 2020 for a period of 3 weeks between 1 March and 30 June 2020.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
The Commission has provided guidance as to measures which Member States can introduce without notification. These include:
- Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
- Measures providing support direct to consumers
- Measures which are already exempt from the notification requirement (discussed further below).
To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:
- The provision of guarantees (including guarantees for 100% of loans)
- The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
- Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
- Measures to recapitalise businesses
- Measures to assist sectors hit particularly hard by the current crisis (eg transport)
- Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus
The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.