Skip to content

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.

Related FAQs

What is the difference between individual and collective consultation?

Where it is envisaged that 20 or more employees will be dismissed at a relevant establishment within a 90 day period or less, then collective consultation is required (in addition to individual consultation) and the company must inform BEIS (using form HR1).

If there are less than 20 dismissals then you are only required to carry out individual consultation.

Can an employee still do volunteer work when on Flexible Furlough?

An employee on Flexible Furlough can take part in volunteer work during hours which you record your employee as being on Flexible Furlough as long as it is for another employer or organisation.

To be clear, if on Flexible Furlough and you’re claiming the grant for them, then they cannot work for you.

As people work part-time and ease back into the business, this is likely going to be a key risk area. You need very clear lines as to working time and non-working time. No replying to emails on days off.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Can NHS or local authority workers be furloughed?

It is envisaged that employees of organisations falling into the first two categories set out above and won’t be eligible for the job retention scheme in relation to the majority of their employees. It is envisaged that NHS Trusts for example are going to require their staff to be working at full capacity where possible. However, the guidance doesn’t definitely exclude public sector organisations from furloughing employees and notably the government expects such organisations to use public money to continue to pay staff and not furlough them, rather than say requires. In reality, it is difficult to see how such an organisation will be able to rely on the scheme, but the guidance doesn’t completely rule it out.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.